Exam 3: Organization: Structure and Culture
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection88 Questions
Exam 3: Organization: Structure and Culture94 Questions
Exam 4: Defining the Project89 Questions
Exam 5: Estimating Project Times and Costs91 Questions
Exam 6: Developing a Project Plan94 Questions
Exam 7: Managing Risk87 Questions
Exam 8: Scheduling Resources and Costs90 Questions
Exam 9: Reducing Project Duration94 Questions
Exam 10: Leadership: Being an Effective Project Manager88 Questions
Exam 11: Managing Project Teams94 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations94 Questions
Exam 13: Progress and Performance Measurement and Evaluation88 Questions
Exam 14: Project Closure88 Questions
Exam 15: International Projects94 Questions
Exam 16: Oversight86 Questions
Exam 17: An Introduction to Agile Project Management85 Questions
Exam 18: Project Management Career Paths35 Questions
Select questions type
Which of the following cultural characteristics relates to the degree to which groups within the organization are encouraged to operate in a coordinated or independent manner?
(Multiple Choice)
4.9/5
(37)
Project management offices were originally developed to make optimal use of scarce project resources.
(True/False)
4.8/5
(43)
In a matrix form of project management, the project managers report directly to a Director of projects, who supervises all projects.
(True/False)
4.9/5
(42)
Elizabeth is considering how to structure a project team that will not directly disrupt ongoing operations.The project needs to be done quickly and a high level of motivation will be needed in order to do that.For this situation, the ______ organization would be the best choice.
(Multiple Choice)
4.7/5
(32)
In which of the following is the balance of authority strongly in favor of the functional managers?
(Multiple Choice)
4.8/5
(35)
The matrix form of project management is predicated on tension between functional managers and project managers who bring critical expertise and perspectives to the project.
(True/False)
4.8/5
(38)
Which of the following is a disadvantage of functional project management organization?
(Multiple Choice)
4.9/5
(26)
There is a strong connection between project management structure, organizational culture, and project success.
(True/False)
4.9/5
(39)
Two of the major disadvantages of the ________ organizational approach to project management are that projects may lack focus and it can take longer to complete projects.
(Short Answer)
4.7/5
(28)
The project structure that is ranked as least effective is _______ organization.
(Multiple Choice)
4.9/5
(39)
__________ were originally developed as a response to the poor track record many companies had in completing projects on time, within budget, and according to plan.
(Short Answer)
4.8/5
(41)
Identify and briefly describe at least two advantages and two disadvantages of having project teams report directly to an existing functional area.
(Short Answer)
4.9/5
(41)
___________ refers to the degree to which employees are encouraged to be aggressive, innovative, and risk seeking.
(Short Answer)
4.8/5
(40)
Which of the following cultural characteristics relates to the degree to which work activities are organized around groups rather than individuals?
(Multiple Choice)
4.9/5
(41)
Culture provides three major functions within today's organizations.Identify and briefly describe those three functions.
(Essay)
4.7/5
(29)
Identify and briefly describe the three forms of organizing projects using the matrix management approach.
(Essay)
4.9/5
(45)
In a Snapshot from Practice, at ________ Corporation, employees put in the hours necessary to get a job done, even if it requires staying up all night; however, they also may stay home to tend to a sick child and do makeup work at some other time.
(Short Answer)
4.9/5
(34)
The project form of project management structure is a good choice when speed of completion of the project without directly disrupting ongoing operations is important.
(True/False)
4.8/5
(47)
Computers R Us is concerned about keeping project costs low and wants to be sure that all pools of expertise are used.Additionally they want to minimize duplication of efforts across projects.Their best choice for project management structure is the _______ organization structure.
(Multiple Choice)
4.9/5
(38)
One of the major disadvantages of the project form of project management structure is that it tends to be more expensive than other forms of organizing.
(True/False)
4.9/5
(30)
Showing 61 - 80 of 94