In a learning curve, the improvement ratio is applied to which of the following items?

Free
(Multiple Choice)
4.7/5
(37)
Correct Answer:
Verified

B

Using a WBS permits the use of different levels of detail for different levels of management.

Free
(True/False)
4.9/5
(39)
Correct Answer:
Verified

True

Identify and briefly describe the four major methods of bottom-up estimating.

Free
(Essay)
4.9/5
(31)
Correct Answer:
Verified

1.template method, 2.parametric procedure applied to specific tasks, 3.detailed estimates from the WBS work packages, and 4.phase estimating

Resource shortages, in the form of people, equipment, or materials, is a good example of

(Multiple Choice)
4.8/5
(31)

Top-down estimates usually are derived from someone who uses experience and/or information to determine the project duration and total cost.

(True/False)
4.9/5
(25)

Top-down estimates are most likely to occur during the ______ phase.

(Multiple Choice)
4.8/5
(34)

Describe the ideal approach for a project manager to develop optimal estimates for a project's time and costs.

(Essay)
4.9/5
(28)

The apportion method is a top-down approach that uses the pooled experience of senior and/or middle managers to estimate the total project duration and cost.

(True/False)
4.8/5
(35)

Which of the following methods is not considered a top-down approach to estimating project time and cost?

(Multiple Choice)
4.8/5
(33)

Reasons why estimating time and cost are important include all of the following except:

(Multiple Choice)
5.0/5
(30)

Under what conditions would the top-down approach to estimating project times and costs be the best choice?

(Essay)
4.9/5
(32)

Estimates that are typically based on estimates of elements found in the work breakdown structure are called ________ estimates.

(Short Answer)
4.9/5
(35)

The ________ approach to estimating project time and cost begins with an overall estimate for the project and then refines estimates for various stages of the project as it is implemented.

(Short Answer)
4.8/5
(37)

Identify and briefly describe the two major categories of estimating project time and costs.

(Essay)
4.8/5
(34)

Identify the factors that should be considered to improve the quality of estimates for project times and costs.

(Essay)
4.9/5
(41)

Which of the following would be the best method for projects where the final product is not known and the uncertainty is very large?

(Multiple Choice)
4.8/5
(30)

The salary of the project manager and her administrative assistant is classified as direct labor costs.

(True/False)
4.9/5
(31)

Which of the following is not one of the bottom-up approaches to estimating project time and cost?

(Multiple Choice)
4.7/5
(40)

Identify the three major categories of project costs and give an example of each.

(Essay)
4.9/5
(26)

Estimates that are usually derived from analogy or mathematical relationships are called ________ estimates.

(Short Answer)
4.8/5
(34)