It is acceptable for arrows to cross one another in a network diagram.

Free
(True/False)
4.9/5
(35)
Correct Answer:
Verified

True

An activity is an element of the project that always requires time but may or may not require resources.

Free
(True/False)
4.9/5
(30)
Correct Answer:
Verified

True

A ________ is an activity that has more than one predecessor.

Free
(Short Answer)
4.8/5
(49)
Correct Answer:
Verified

merge activity
Explanation: Merge activity is an activity that has more than one activity immediately preceding it (more than one dependency arrow flowing to it).

The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag?

(Multiple Choice)
4.7/5
(36)

Nodes on an AON project network represent:

(Multiple Choice)
4.9/5
(33)

The ________ calculates the earliest times that activities can be started or finished.

(Short Answer)
4.8/5
(37)

Experience suggests that when there are multiple starts, a common start node should not be used to indicate a clear project beginning on the network.Similarly, a single project end node can be used to indicate a clear ending.

(True/False)
4.9/5
(32)

Project networks are built using nodes and arrows.

(True/False)
4.8/5
(36)

A ____________ lag exists if debug cannot begin until two days after coding has started and that coding must be completed four days before debug can be completed.

(Short Answer)
4.8/5
(43)

Gantt charts are popular because they represent an easy-to-understand, clear picture on a time-scaled horizon.

(True/False)
4.8/5
(33)

The ________ calculates the critical path and determines how long an activity can be delayed without delaying the project.

(Short Answer)
4.8/5
(38)

Free slack applies to an entire project network.

(True/False)
4.8/5
(31)

Which of the following is provided by a project network but not by the work breakdown structure?

(Multiple Choice)
4.7/5
(32)

The backward pass though a project network determines how long an activity can be delayed without impacting the completion date of the project.

(True/False)
4.8/5
(30)

An item on a project network is Design Software Completed.This is best described as a(n)

(Multiple Choice)
4.9/5
(32)

The laying pipe example in the text illustrates the concept of

(Multiple Choice)
4.7/5
(30)

In the ________ technique, an activity with a long duration is broken into smaller segments so that the following activities can begin sooner.

(Short Answer)
4.8/5
(30)

The critical path in a project network is the

(Multiple Choice)
4.9/5
(41)

Which of the following represents an activity on an AON project network?

(Multiple Choice)
4.9/5
(50)

What is a hammock activity and give an example?

(Essay)
4.8/5
(24)