Exam 9: Reducing Project Duration

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The president of a software company remarks in a speech that new technologically advanced software will be available in one year.This is an example of reducing project duration caused by:

Free
(Multiple Choice)
4.9/5
(30)
Correct Answer:
Verified

A

Identify options for accelerating a project schedule when resources are not constrained.

Free
(Essay)
4.8/5
(43)
Correct Answer:
Verified

1.outsourcing project work, 2.scheduling overtime, 3.adding resources, 4.establish a core project team, and 5.do it twice.

Which of the following is the most common method for shortening project time?

Free
(Multiple Choice)
4.8/5
(30)
Correct Answer:
Verified

A

The easiest way to add more resources to a project is not to add more people, but to schedule ________.

(Short Answer)
4.9/5
(33)

Sometimes very high ________ costs are recognized before a project begins and reducing these costs through shorter project durations becomes a high priority.

(Short Answer)
4.8/5
(38)

When the project team is salaried, which of the following is the preferred choice for accelerating project completion?

(Multiple Choice)
4.9/5
(41)

The Snapshot from Practice which detailed the Northridge earthquake demonstrated the importance of reducing a project's ______.

(Short Answer)
4.9/5
(41)

What is Critical-chain (C-C) project management and why can it be of benefit to project managers?

(Essay)
4.8/5
(34)

The most common method for shortening project time is to

(Multiple Choice)
4.8/5
(37)

The project direct-cost line near the normal point is usually:

(Multiple Choice)
4.9/5
(37)

Crash cost is the incremental cost incurred when an activity is reduced in duration.

(True/False)
4.8/5
(35)

When a politician makes a public statement that a new building will be available in two years, a(n) ________ duration has reduced the project duration.

(Short Answer)
4.9/5
(30)

Which of the following is not considered a project indirect cost?

(Multiple Choice)
4.9/5
(32)

Crash time is the greatest time reduction possible under realistic conditions.

(True/False)
4.9/5
(30)

The direct costs for completing an activity as early as possible is called its ________.

(Short Answer)
4.9/5
(35)

What is crashing and include a discussion of crash time and crash cost?

(Essay)
4.9/5
(36)

One way of reducing project costs is identifying tasks that _________ can do themselves.

(Multiple Choice)
4.9/5
(39)

____ costs are incurred when completing an activity in its realistically shortest time.

(Multiple Choice)
4.8/5
(35)

The shortest possible time an activity can be completed realistically is called ___ time.

(Multiple Choice)
4.8/5
(46)

Why is the project duration with the lowest direct costs seldom the optimum duration for a project?

(Essay)
4.8/5
(36)
Showing 1 - 20 of 94
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)