Exam 13: Progress and Performance Measurement and Evaluation
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection88 Questions
Exam 3: Organization: Structure and Culture94 Questions
Exam 4: Defining the Project89 Questions
Exam 5: Estimating Project Times and Costs91 Questions
Exam 6: Developing a Project Plan94 Questions
Exam 7: Managing Risk87 Questions
Exam 8: Scheduling Resources and Costs90 Questions
Exam 9: Reducing Project Duration94 Questions
Exam 10: Leadership: Being an Effective Project Manager88 Questions
Exam 11: Managing Project Teams94 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations94 Questions
Exam 13: Progress and Performance Measurement and Evaluation88 Questions
Exam 14: Project Closure88 Questions
Exam 15: International Projects94 Questions
Exam 16: Oversight86 Questions
Exam 17: An Introduction to Agile Project Management85 Questions
Exam 18: Project Management Career Paths35 Questions
Select questions type
When measuring percent complete in the monitoring phase of the project, it is common to limit the amount earned to __________ until the work package is 100 percent complete.
Free
(Short Answer)
4.8/5
(37)
Correct Answer:
80 or 90 percent
Explanation: When measuring percent complete in the monitoring phase of the project, it is common to limit the amount earned to 80 or 90 percent until the work package is 100 percent complete.
The PCIC index measures the project percent complete in relation to the resources that have actually been used so far on the project.
Free
(True/False)
4.8/5
(29)
Correct Answer:
True
A concept of ________ is necessary to get a realistic estimate of performance against a time-phased budget.
Free
(Short Answer)
4.9/5
(33)
Correct Answer:
earned value
Explanation: Earned value is necessary to provide a realistic estimate of performance against a time-phased budget.Earned value (EV) is defined as the budgeted cost of the work performed.
The best method for assigning costs to the baseline is to establish frequent __________ over the duration of the work package.
(Short Answer)
4.8/5
(35)
Small refinements that eventually build to be major changes are known as:
(Multiple Choice)
4.9/5
(32)
Briefly describe the general structure of a project monitoring information system for control.
(Essay)
4.9/5
(32)
The major reasons for creating a baseline are to monitor and report progress and to estimate cash flow.
(True/False)
4.8/5
(28)
Scope Creep refers to any significant changes made in the project once it is underway.
(True/False)
4.9/5
(39)
The third step in the project control process of the measurement and evaluation of project performance is to:
(Multiple Choice)
4.9/5
(31)
An SPI index of 1.22 indicates that the project is ________ schedule.
(Short Answer)
4.8/5
(42)
The original earned value cost/schedule system was pioneered by the U.S.Department of Defense in the 1960s.
(True/False)
4.9/5
(29)
The first step in creating a project control system for measuring and evaluating project performance is to ________.
(Short Answer)
4.9/5
(37)
Which of the following methods will measure the cost efficiency of the work accomplished to date?
(Multiple Choice)
4.9/5
(38)
The last step in the project control process of the measurement and evaluation of project performance is to:
(Multiple Choice)
4.9/5
(36)
In reviewing the budget report of a project, you notice that spending on the project is running about ten percent over plan.Is the project in trouble? Why or why not?
(Essay)
4.8/5
(35)
The ________ is a tool used to monitor past project schedule performance and current performance and to estimate future schedule trends.
(Short Answer)
4.8/5
(39)
Identify and briefly describe the three percent complete rules for placing costs in baselines.
(Essay)
4.9/5
(40)
Which of the following will calculate the estimated cost to complete the project?
(Multiple Choice)
4.8/5
(34)
Showing 1 - 20 of 88