Exam 6: Project Time Management
Exam 1: Introduction to Project Management100 Questions
Exam 2: The Project Management and Information Technology Context80 Questions
Exam 3: The Project Management Process Groups: A Case Study82 Questions
Exam 4: Project Integration Management100 Questions
Exam 5: Project Scope Management75 Questions
Exam 6: Project Time Management100 Questions
Exam 7: Project Cost Management100 Questions
Exam 8: Project Quality Management100 Questions
Exam 9: Project Human Resource Management100 Questions
Exam 10: Project Communications Management99 Questions
Exam 11: Project Risk Management99 Questions
Exam 12: Project Procurement Management75 Questions
Select questions type
The ______________________________ is based on the fact that,like a chain with its weakest link,any complex system at any point in time often has only one aspect or constraint that limits its ability to achieve more of its goal.
(Short Answer)
4.8/5
(28)
The main outputs of estimating activity resources include the activity list and attributes,project scope statement,milestone list,and organizational process assets.
(True/False)
4.9/5
(31)
____ dependencies involve relationships between project and non-project activities.
(Multiple Choice)
4.8/5
(31)
Project management software highlights the critical path in ____ on a network diagram.
(Multiple Choice)
4.8/5
(36)
Many project management software programs come with ____________________ or sample files.
(Short Answer)
5.0/5
(31)
Project management software does not have the capacity to automatically generate network diagrams and calculate the critical path(s)for the project.
(True/False)
4.9/5
(37)
In a ____ relationship,one task cannot finish before another finishes.
(Multiple Choice)
4.8/5
(45)
____ is a network diagramming technique used to predict total project duration.
(Multiple Choice)
4.9/5
(32)
Duration estimates are often provided as a discrete number,such as four weeks,or as a range,such as three to five weeks,or as a(n)____________________.
(Short Answer)
4.8/5
(44)
In a Gantt chart created in Microsoft Project,a black diamond symbol represents a milestone.
(True/False)
4.7/5
(35)
Project managers often illustrate progress with a ____ showing key deliverables and activities.
(Multiple Choice)
4.9/5
(38)
The ultimate goal of ____ is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project.
(Multiple Choice)
4.7/5
(33)
____________________ is the one variable in project scheduling that has the least amount of flexibility.
(Short Answer)
4.8/5
(37)
It is not necessary to complete all of theactivities on the network diagram in order for the project to finish.
(True/False)
4.8/5
(36)
_________________________ involves the processes required to ensure timely completion of a project.
(Short Answer)
4.8/5
(29)
A(n)____________________ on a project is a significant event that normally has no duration.
(Short Answer)
4.8/5
(31)
Project schedules grow out of the basic documents that initiate a project.
(True/False)
4.7/5
(42)
____ involves analyzing activity sequences,activity resource estimates,and activity duration estimates to create the project schedule.
(Multiple Choice)
4.9/5
(49)
Showing 41 - 60 of 100
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)