Exam 6: Project Time Management
Exam 1: Introduction to Project Management100 Questions
Exam 2: The Project Management and Information Technology Context80 Questions
Exam 3: The Project Management Process Groups: A Case Study82 Questions
Exam 4: Project Integration Management100 Questions
Exam 5: Project Scope Management75 Questions
Exam 6: Project Time Management100 Questions
Exam 7: Project Cost Management100 Questions
Exam 8: Project Quality Management100 Questions
Exam 9: Project Human Resource Management100 Questions
Exam 10: Project Communications Management99 Questions
Exam 11: Project Risk Management99 Questions
Exam 12: Project Procurement Management75 Questions
Select questions type
Outputs from ____ include work performance measurements,organizational process assets updates,change requests,project management plan updates,and project document updates.
(Multiple Choice)
4.8/5
(38)
____ use(s)probabilistic time estimates-duration estimates based on using optimistic,most likely,and pessimistic estimates of activity durations-instead of one specific or discrete duration estimate.
(Multiple Choice)
4.7/5
(39)
By using the PERT weighted average for each activity duration estimate,the total project duration estimate does not account for the risk or uncertainty in the individual activity estimates.
(True/False)
4.7/5
(29)
Duration only includes the actual amount of time worked on an activity.
(True/False)
4.9/5
(38)
The goal of ____ is to know the status of the schedule,influence the factors that cause schedule changes,determine that the schedule has changed,and manage changes when they occur.
(Multiple Choice)
4.8/5
(44)
____ involves identifying and documenting the relationships between project activities.
(Multiple Choice)
4.9/5
(40)
Even though the delivery of new hardware may not be in the scope of a project,you should add an external dependency to it if required project activities depend on that delivery.
(True/False)
4.8/5
(35)
____ is the amount of time an activity can be delayed from its early start without delaying the planned project finish date.
(Multiple Choice)
4.8/5
(29)
After defining project activities,the next step in project time management is sequencing them or determining their dependencies.
(True/False)
4.8/5
(39)
In a ____ relationship,the "from" activity cannot start until the "to" activity is started.
(Multiple Choice)
5.0/5
(43)
Network diagrams are the preferred technique for showing activity discretionary dependencies.
(True/False)
4.7/5
(34)
What is the Theory of Constraints? What is Critical Chain Scheduling?
(Essay)
4.9/5
(43)
Many information technology projects are failures in terms of meeting scope,time,and cost projections.
(True/False)
4.9/5
(34)
A(n)____________________ for a project is the series of activities that determine the earliest time by which the project can be completed.
(Short Answer)
4.9/5
(35)
One of PERT's main disadvantages is that it involves more work than CPM.
(True/False)
4.8/5
(31)
____ involves estimating the number of work periods that are needed to complete individual activities.
(Multiple Choice)
4.9/5
(37)
A(n)____________________ Gantt chart compares planned and actual project schedule information.
(Short Answer)
4.9/5
(34)
The main outputs of the ____ process are an activity list,activity attributes,and milestone list.
(Multiple Choice)
4.8/5
(40)
Showing 21 - 40 of 100
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)