Exam 3: Developing Project Proposals
Exam 1: Project Management Concepts79 Questions
Exam 2: Identifying and Selecting Projects70 Questions
Exam 3: Developing Project Proposals112 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence129 Questions
Exam 5: Developing the Schedule86 Questions
Exam 6: Resource Utilization22 Questions
Exam 7: Determining Costs, Budget, and Earned Value69 Questions
Exam 8: Managing Risk45 Questions
Exam 9: Closing the Project42 Questions
Exam 10: The Project Manager129 Questions
Exam 11: The Project Team225 Questions
Exam 12: Project Communication and Documentation124 Questions
Exam 13: Project Management Organizational Structures65 Questions
Select questions type
The contractor must notify the customer immediately of any actual or anticipated cost savings or schedule delays.
(True/False)
4.9/5
(42)
If a customer has stated the budget in the RFP, the customer might reject proposals that have cost estimates greater than the budget without further review of the proposal.
(True/False)
4.8/5
(37)
The schedule can include times for major tasks and key milestones to show sequence and interdependencies of the tasks.
(True/False)
4.9/5
(37)
A ballpark estimate is acceptable for the proposal.There will be time to figure out the budget after the contract is won.
(True/False)
4.8/5
(32)
In , the customer usually requires that, throughout the project, the contractor regularly compares actual expenditures with the proposed budget and reforecasts cost at-completion, comparing it with the original proposed price.
(Multiple Choice)
4.8/5
(37)
It is unethical to submit an unsolicited proposal to a customer.
(True/False)
4.8/5
(32)
A contractor's preRFP/proposal efforts are crucial to establishing the foundation for eventually winning a contract
from the customer.
(True/False)
4.8/5
(36)
Contractors measure the success of their proposal efforts by the number of times their proposals are selected by customers and/or by the total dollar value of their proposals that are selected.
(True/False)
4.7/5
(34)
Waiting to develop a proposal until an RFP is announced is important to be sure all the information is available.
(True/False)
4.9/5
(32)
A complex proposal is a technical report with charts and figures to explain the approach.
(True/False)
4.9/5
(33)
A proposal manager is required to have a consistent, comprehensive proposal by the due date in the RFP.
(True/False)
4.8/5
(31)
Including complicated graphics in a proposal demonstrates a contractor's advanced skill and shows specific technical expertise.
(True/False)
4.7/5
(32)
The proposal should include a lengthy, detailed list of activities to show planning has been well thought out by the contractor.
(True/False)
4.8/5
(43)
The contractor needs to obtain advance approval from the customer before hiring a subcontractor to perform a project task.
(True/False)
4.9/5
(30)
Quantitative and qualitative benefits to the customer should be stated to help convince the customer of the value of the proposed result.
(True/False)
4.7/5
(31)
Changes can be initiated by the customer or be proposed by the contractor.Some changes may necessitate a change in price increase or decrease); others may not.
(True/False)
4.9/5
(28)
Sleeping on a contradictory issue and providing a thoughtful answer the next day
(Multiple Choice)
4.8/5
(40)
Showing 21 - 40 of 112
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)