Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence
Exam 1: Project Management Concepts79 Questions
Exam 2: Identifying and Selecting Projects70 Questions
Exam 3: Developing Project Proposals112 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence129 Questions
Exam 5: Developing the Schedule86 Questions
Exam 6: Resource Utilization22 Questions
Exam 7: Determining Costs, Budget, and Earned Value69 Questions
Exam 8: Managing Risk45 Questions
Exam 9: Closing the Project42 Questions
Exam 10: The Project Manager129 Questions
Exam 11: The Project Team225 Questions
Exam 12: Project Communication and Documentation124 Questions
Exam 13: Project Management Organizational Structures65 Questions
Select questions type
Each activity in a network diagram is represented by a box in the , and the of the activity is written within the box.
(Multiple Choice)
4.7/5
(37)
All branches of the WBS have to be broken down to the same level.
(True/False)
4.7/5
(30)
Activities define more generally than work packages how the work will get done.
(True/False)
4.9/5
(40)
Clear, ambiguous acceptance criteria for all deliverables are important because they are the basis for verifying that the project scope has been completed in accordance with the customer's requirements and expectations.
(True/False)
4.8/5
(41)
To draw a , start by drawing the activities in boxes in their logical sequence and connecting them with arrows to show the required dependent relationships, as the project should be performed from start to completion.
(Multiple Choice)
4.8/5
(30)
The work package includes all of the specific work activities that need to be performed to produce the deliverable associated with that work package.
(True/False)
4.7/5
(39)
The customer may randomly select certain work elements to review in order to determine whether they are being done in conformance with quality standards and requirements.
(True/False)
4.7/5
(29)
The states the specific deliverable that is expected to be completed from the work activities associated with each lowest level-work package.
(Multiple Choice)
4.8/5
(35)
The all of the lowest-level work packages in the work breakdown structure constitutes completion of the project work scope.
(Multiple Choice)
4.8/5
(34)
The description of an activity in a network diagram usually starts with a .
(Multiple Choice)
4.8/5
(40)
The is the tangible end product that the project team or contractor must produce and deliver in order for the sponsor or customer to achieve the expected benefits from implementing the project.
(Multiple Choice)
4.8/5
(39)
A network diagram is a technique for organizing and subdividing all the project work and deliverables into more manageable components.
(True/False)
4.9/5
(34)
It is easier to define the details for , but as the project progresses or moves from phase to phase, the project team or contractor can progressively elaborate the details as more information is known or becomes clear.
(Multiple Choice)
5.0/5
(30)
Different project teams might create somewhat different work breakdown structures for the same project.
(True/False)
4.8/5
(32)
It is common to progressively elaborate the network diagram
(Multiple Choice)
4.9/5
(34)
Designating as having primary responsibility can cause confusion and increase the risk that some work will "fall through the cracks," because each may assume that the other is going to do it.
(Multiple Choice)
4.9/5
(38)
A network diagram is a tool for arranging the specific activities in the and defining their .
(Multiple Choice)
4.9/5
(38)
The is a roadmap that displays how all the specific activities fit together to accomplish the project work scope.
(Multiple Choice)
4.8/5
(32)
The project objective must be clear, attainable, specific, and measurable.
(True/False)
4.9/5
(32)
In the network diagram for the following list, what activity immediately follows activity B? 

(Multiple Choice)
4.9/5
(26)
Showing 101 - 120 of 129
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)