Exam 9: Project Communication,tracking,and Reporting
Exam 1: The Nature of Information Technology Projects56 Questions
Exam 2: Initializing and Conceptualizing the IT Project63 Questions
Exam 3: The Project Infrastructure61 Questions
Exam 4: The Human Side of Project Management53 Questions
Exam 5: Defining and Managing Project and Product Scope49 Questions
Exam 6: The Work Breakdown Structure and Project Estimation66 Questions
Exam 7: The Project Schedule and Budget64 Questions
Exam 8: Managing Project Risk69 Questions
Exam 9: Project Communication,tracking,and Reporting63 Questions
Exam 10: It Project Quality Management71 Questions
Exam 11: Managing Organizational Change, resistance, and Conflict81 Questions
Exam 12: Project Procurement Management and Outsourcing73 Questions
Exam 13: Leadership and Ethics75 Questions
Exam 14: Project Implementation, closure, and Evaluation65 Questions
Select questions type
A metric that provides an estimate for completing the scheduled work that remains once the project is started is called the
(Multiple Choice)
4.9/5
(40)
Planned value PV)is the planned or budgeted cost of work scheduled for an activity or component of the WBS.
(True/False)
4.8/5
(32)
The metric that provides an estimate of the most likely total or final cost of the project based on the project's performance and any risks that should be considered is the:
(Multiple Choice)
4.8/5
(37)
A project metric should be obtained from observable,quantifiable data that allows the team and other stakeholders to gauge the efficiency and effectiveness of the work being done.
(True/False)
4.8/5
(39)
Given the advances that have been made in telecommunications and IT technology in general,there is little value or necessity today for Face-to-Face F2F)meetings.
(True/False)
4.9/5
(44)
The Estimate At Completion EAC)is a project metric that can be used to estimate the most likely total or final cost of the project based on the project's performance and any risks that should be considered.
(True/False)
4.8/5
(30)
Information distribution includes all of the following EXCEPT:
(Multiple Choice)
4.8/5
(37)
Barring a change in project scope and given a Cost Performance Index CPI)that is less than 1,the most reasonable inference to draw is that:
(Multiple Choice)
4.9/5
(39)
Generally,the more metrics one adopts,the greater the project control.
(True/False)
4.8/5
(37)
Budget At Completion BAC)is the total planned cost of a project.
(True/False)
4.7/5
(38)
A _________ describes the present state of the project and provides compares the project's actual progress to the baseline plan.
(Multiple Choice)
4.8/5
(38)
If a stakeholder has been judged to adversarial and having a vested interest in the failure of your project,it would probably be wise to keep him/her out of the communication loop.
(True/False)
4.9/5
(36)
The project manager must have a clear picture of how the actual progress or work compares to the baseline plan in order to make well-informed decisions,take appropriate actions,or to make adjustments to the project plan.
(True/False)