Exam 9: Project Communication,tracking,and Reporting

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Why is effective and efficient communication vital to a project?

(Essay)
4.9/5
(48)

A metric that provides an estimate for completing the scheduled work that remains once the project is started is called the

(Multiple Choice)
4.9/5
(40)

What is a progress report?

(Essay)
4.7/5
(43)

Planned value PV)is the planned or budgeted cost of work scheduled for an activity or component of the WBS.

(True/False)
4.8/5
(32)

The metric that provides an estimate of the most likely total or final cost of the project based on the project's performance and any risks that should be considered is the:

(Multiple Choice)
4.8/5
(37)

A project metric should be obtained from observable,quantifiable data that allows the team and other stakeholders to gauge the efficiency and effectiveness of the work being done.

(True/False)
4.8/5
(39)

Given the advances that have been made in telecommunications and IT technology in general,there is little value or necessity today for Face-to-Face F2F)meetings.

(True/False)
4.9/5
(44)

The Estimate At Completion EAC)is a project metric that can be used to estimate the most likely total or final cost of the project based on the project's performance and any risks that should be considered.

(True/False)
4.8/5
(30)

Actual Cost AC is __________

(Multiple Choice)
4.8/5
(31)

Information distribution includes all of the following EXCEPT:

(Multiple Choice)
4.8/5
(37)

Barring a change in project scope and given a Cost Performance Index CPI)that is less than 1,the most reasonable inference to draw is that:

(Multiple Choice)
4.9/5
(39)

Schedule Variance SV)is __________

(Multiple Choice)
4.8/5
(37)

Generally,the more metrics one adopts,the greater the project control.

(True/False)
4.8/5
(37)

Budget At Completion BAC)is the total planned cost of a project.

(True/False)
4.7/5
(38)

A _________ describes the present state of the project and provides compares the project's actual progress to the baseline plan.

(Multiple Choice)
4.8/5
(38)

What is a status report?

(Essay)
4.8/5
(33)

If a stakeholder has been judged to adversarial and having a vested interest in the failure of your project,it would probably be wise to keep him/her out of the communication loop.

(True/False)
4.9/5
(36)

The project manager must have a clear picture of how the actual progress or work compares to the baseline plan in order to make well-informed decisions,take appropriate actions,or to make adjustments to the project plan.

(True/False)
4.9/5
(46)

Estimate at Completion EAC is __________

(Multiple Choice)
5.0/5
(42)

Describe the PMBOK area called project communications management.

(Essay)
4.7/5
(38)
Showing 21 - 40 of 63
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)