Exam 15: Short-Term Scheduling
Exam 1: Operations and Productivity126 Questions
Exam 2: Operations Strategy in a Global Environment135 Questions
Exam 3: Project Management121 Questions
Exam 4: Forecasting144 Questions
Exam 5: Sustainability in the Supply Chain and Design of Goods and Services137 Questions
Exam 6: Managing Quality129 Questions
Exam 7: Process Strategy and Sustainability131 Questions
Exam 8: Location Strategies139 Questions
Exam 9: Layout Strategies161 Questions
Exam 10: Human Resources,job Design,and Work Measurement192 Questions
Exam 11: Supply-Chain Management145 Questions
Exam 12: Inventory Management168 Questions
Exam 13: Aggregate Planning134 Questions
Exam 14: Material Requirements Planning Mrpand ERP169 Questions
Exam 15: Short-Term Scheduling139 Questions
Exam 16: Jit and Lean Operations137 Questions
Exam 17: Maintenance and Reliability130 Questions
Exam 18: Statistical Process Control156 Questions
Exam 19: Capacity and Constraint Management107 Questions
Exam 20: Supply Chain Management Analytics55 Questions
Exam 21: Decision-Making Tools97 Questions
Exam 22: Linear Programming100 Questions
Exam 23: Transportation Models94 Questions
Exam 24: Waiting-Line Models135 Questions
Exam 25: Learning Curves111 Questions
Exam 26: Simulation92 Questions
Select questions type
Which of the following is not an effectiveness criterion for scheduling?
Free
(Multiple Choice)
4.8/5
(39)
Correct Answer:
E
The jobs listed below needed to be completed.Assume that it is now day 140.If the jobs are sequenced according to longest processing time rule,what is the lateness of job A? 

Free
(Multiple Choice)
4.9/5
(38)
Correct Answer:
D
Which of the following are limitations of rules-based dispatching systems?
(Multiple Choice)
4.9/5
(31)
Use Johnson's rule to determine the optimal sequencing for the five jobs to be processed on two machines in a fixed order (Machine 1 before Machine 2).The processing times in hours are given in the table below.
a.What is the optimal sequence?
b.What is the total flow time for this sequence?
c.Which job is the first to be scheduled? Is it scheduled to be the first job or the last? Explain.


(Essay)
4.8/5
(29)
At Morgan's Transformer Rebuilding,a set of five jobs is ready for dispatching to a machine centre.The processing times and due dates for the jobs are given in the table below.Use shortest processing time to sequence the jobs,and calculate the average completion time,the average job lateness,and the average number of jobs in the machine centre.


(Essay)
4.8/5
(41)
Which file contains important information regarding an item's flow through the shop?
(Multiple Choice)
4.9/5
(34)
Use Johnson's rule to determine the optimal sequencing for the five jobs to be processed on two machines in a fixed order (Machine 1 before Machine 2).The processing times are given in the table below.
a.What is the optimal sequence?
b.What is the total flow time for this sequence?


(Essay)
5.0/5
(34)
Eight jobs have been sequenced at a single work centre.Total processing time for the eight jobs is 34 hours and total flow time for the sequence is 85 hours.For this schedule,utilization is ________ and average jobs in the system is ________.
(Multiple Choice)
4.8/5
(37)
Using LPT priority would result in what sequence for Jobs A,B,C,and D if their process times are 4,6,5,2 respectively?
(Multiple Choice)
4.8/5
(35)
Five jobs are waiting for processing through two work centres.Their processing time (in minutes)at each work centre is contained in the table below.Each job requires work centre Sigma before work centre Delta.According to Johnson's rule,what sequence of jobs will minimize the completion time for all jobs? 

(Multiple Choice)
4.7/5
(34)
________ scheduling begins with the due date and schedules the final operation first and the other job steps in reverse order.
(Essay)
4.8/5
(36)
Which of the following is an aid used to monitor jobs in process?
(Multiple Choice)
4.8/5
(28)
Gantt charts are useful for scheduling jobs,but not for loading them.
(True/False)
4.7/5
(36)
If job 5 takes 3,4,or 5 hours to be completed by workers A,B,and C,respectively,what would the row values for job 5 be after performing Step 1A of the assignment method?
(Multiple Choice)
4.9/5
(34)
The correct sequence from longest to smallest duration scheduling is
(Multiple Choice)
4.7/5
(39)
The priority rule that sequences jobs using the smallest ratio of due date from today to processing time is
(Multiple Choice)
4.7/5
(35)
The first step in level material use is to combine orders into a few large batches in order to utilize economies of scale.
(True/False)
4.8/5
(27)
Air Canada uses mathematical short-term scheduling techniques and a high-tech nerve centre to manage the rapid rescheduling necessary to cope with weather delays and similar disruptions.