Exam 3: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The phases of project management are

Free
(Multiple Choice)
4.7/5
(35)
Correct Answer:
Verified

A

________ is the amount of time an individual activity in a network can be delayed without delaying the entire project.

Free
(Essay)
4.8/5
(36)
Correct Answer:
Verified

Slack time

Slack is the amount of time an activity can be delayed without delaying the entire project.

Free
(True/False)
5.0/5
(30)
Correct Answer:
Verified

True

Which of the following statements regarding PERT analysis is true?

(Multiple Choice)
4.8/5
(37)

An activity on a PERT network has these time estimates: optimistic = 2,most likely = 5,and pessimistic = 10.Its expected time is

(Multiple Choice)
4.8/5
(39)

Which of the following statements regarding PERT times is true?

(Multiple Choice)
4.9/5
(30)

The critical path for the network activities shown below is ________ with duration ________. The critical path for the network activities shown below is ________ with duration ________.

(Multiple Choice)
4.9/5
(28)

Define slack.

(Essay)
4.8/5
(36)

What are the earliest activity start time and latest activity start time,and how are they computed?

(Essay)
4.9/5
(35)

The PERT pessimistic time estimate is an estimate of the minimum time an activity will require.

(True/False)
4.8/5
(25)

Which of the following statements regarding time-cost tradeoffs in CPM networks is false?

(Multiple Choice)
4.8/5
(34)

A project being analyzed by PERT has 60 activities,13 of which are on the critical path.If the estimated time along the critical path is 214 days with a project variance of 100,the probability that the project will take 224 days or more to complete is

(Multiple Choice)
4.7/5
(38)

A simple CPM network has three activities,D,E,and F.D is an immediate predecessor of E and of F.E is an immediate predecessor of F.The activity durations are D = 5,E = 4,F = 9.

(Multiple Choice)
4.9/5
(50)

Briefly discuss what is meant by critical path analysis.What are critical path activities and why are they important?

(Essay)
4.8/5
(32)

What are the three phases of a project? Describe each in a sentence or two.

(Essay)
5.0/5
(33)

A network consists of the activities in the following list.Times are given in weeks. A network consists of the activities in the following list.Times are given in weeks.    a.Draw the network diagram. b.Calculate the ES,EF,LS,LF,and Slack for each activity. c.What is project completion time? a.Draw the network diagram. b.Calculate the ES,EF,LS,LF,and Slack for each activity. c.What is project completion time?

(Essay)
4.9/5
(35)

Work Breakdown Structure is a useful tool in project management because it addresses the timing of individual work elements.

(True/False)
4.9/5
(41)

If an activity whose normal duration is 13 days can be shortened to 10 days for an added cost of $1,500,the crash cost per period is

(Multiple Choice)
4.9/5
(28)

In PERT analysis,the identification of the critical path can be incorrect if a noncritical activity takes substantially more than its expected time.

(True/False)
4.9/5
(39)

In project management,crashing an activity must consider the impact on all paths in the network.

(True/False)
4.9/5
(42)
Showing 1 - 20 of 121
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)