Daily capacity of a product layout is determined by

Free
(Multiple Choice)
4.8/5
(30)
Correct Answer:
Verified

A

The concept of customizing in a warehouse layout

Free
(Multiple Choice)
4.9/5
(30)
Correct Answer:
Verified

D

Cycle time is the maximum time that the product is allowed at each workstation.

Free
(True/False)
4.8/5
(34)
Correct Answer:
Verified

True

An assembly line has been designed to make battery-powered beverage mixers.Task details are shown in the table below: An assembly line has been designed to make battery-powered beverage mixers.Task details are shown in the table below:    a.What is the assigned cycle time (in minutes)? b.What is the maximum output rate of this line in mixers per hour? c.What is the total idle time per cycle? d.What is the assembly line's efficiency? a.What is the assigned cycle time (in minutes)? b.What is the maximum output rate of this line in mixers per hour? c.What is the total idle time per cycle? d.What is the assembly line's efficiency?

(Essay)
4.8/5
(32)

A disadvantage of product-oriented layout is that

(Multiple Choice)
4.8/5
(33)

________ is that element of balancing a work cell that superficially resembles cycle time.

(Essay)
4.9/5
(38)

An assembly line consists of 158 tasks grouped into 32 workstations.The sum of all task times is 105 minutes.The largest assigned cycle time is 4 minutes.The efficiency of this line is approximately

(Multiple Choice)
4.9/5
(35)

The ________ is a non-numeric method for determining which departments are located near one another,and which departments are kept farther apart.

(Essay)
4.8/5
(37)

Briefly explain what "slotting" is.Why is slotting considered a "controversial" practice? What ethical issues might arise with regard to slotting?

(Essay)
4.8/5
(31)

Identify the seven fundamental layout strategies.Describe the use of each one very briefly.

(Essay)
5.0/5
(32)

A company is designing a product layout for a new product.It plans to use this production line eight hours a day in order to meet a schedule of 400 units per day.The tasks necessary to produce this product are detailed in the table below. A company is designing a product layout for a new product.It plans to use this production line eight hours a day in order to meet a schedule of 400 units per day.The tasks necessary to produce this product are detailed in the table below.    a.Draw the network described in the table. b.Without regard to a production schedule,what is the minimum possible cycle time (in seconds)for this situation;what is the maximum? c.What is the required cycle time (in seconds)in order to meet the schedule? d.What is the theoretical minimum number of workstations needed to meet the schedule? e.Balance this line using longest processing time. f.What is the efficiency of the balance obtained in part e? a.Draw the network described in the table. b.Without regard to a production schedule,what is the minimum possible cycle time (in seconds)for this situation;what is the maximum? c.What is the required cycle time (in seconds)in order to meet the schedule? d.What is the theoretical minimum number of workstations needed to meet the schedule? e.Balance this line using longest processing time. f.What is the efficiency of the balance obtained in part e?

(Essay)
4.7/5
(39)

Cycle time is computed as

(Multiple Choice)
4.9/5
(46)

A company is trying to balance production between 3 workstations on an assembly line.Currently there are 5 tasks that need to be performed.These tasks,ABCDE,have required times of 2 minutes,4 minutes,1 minutes,3 minutes,and 10 minutes respectively.The assembly line needs to produce 40 units per day to meet demand and can work for up to 8 hours each day. A.What is the required cycle time? B.What is the theoretical minimum # of workstations? C.Assign the tasks according to shortest task time. D.Is there a better way to divide the work than in Part C?

(Essay)
4.8/5
(38)

The biggest advantage of a product layout is its flexibility to handle a varied product mix.

(True/False)
4.8/5
(24)

The assumption of stability of demand is important for justifying which of the following layout types?

(Multiple Choice)
4.7/5
(36)

A focused work center is well suited to the production of a large family of products requiring similar processing,even if their demands are not very stable.

(True/False)
4.8/5
(42)

If a layout problem is solved by use of "heuristics," this means that

(Multiple Choice)
4.8/5
(34)

A work cell is scheduled to build 120 digital light processor (DLP)assemblies each week.These assemblies are later installed into home theatre projection systems.The work cell has 7.5 hours of productive work each day,six days per week.What is takt time for this cell?

(Essay)
4.8/5
(41)

An airport is trying to balance where to place three airlines.The distance between terminals and the number of trips that travelers make between airlines per day are listed.Find the assignment that minimizes the distance travelers must walk. An airport is trying to balance where to place three airlines.The distance between terminals and the number of trips that travelers make between airlines per day are listed.Find the assignment that minimizes the distance travelers must walk.

(Essay)
5.0/5
(35)

Explain what the purpose of assembly line balancing is.Describe briefly how it is done.Explain how assembly line balancing supports the needs of product layout.