Exam 16: Just-In-Time and Lean Options
Exam 1: Operations and Productivity126 Questions
Exam 2: Operations Strategy in a Global Environment135 Questions
Exam 3: Project Management123 Questions
Exam 4: Forecasting142 Questions
Exam 5: Design of Goods and Services137 Questions
Exam 6: Managing Quality130 Questions
Exam 7: Process Strategy129 Questions
Exam 8: Location Strategies140 Questions
Exam 9: Layout Strategies161 Questions
Exam 10: Human Resources, Job Design, and Work Measurement191 Questions
Exam 11: Supply-Chain Management145 Questions
Exam 12: Inventory Management171 Questions
Exam 13: Aggregate Planning134 Questions
Exam 14: Material Requirements Planning Mrp and Erp172 Questions
Exam 15: Short-Term Scheduling139 Questions
Exam 16: Just-In-Time and Lean Options138 Questions
Exam 17: Maintenance and Reliability130 Questions
Exam 18: Statistical Tools for Managers97 Questions
Exam 19: Acceptance Sampling99 Questions
Exam 20: The Simplex Method of Linear Programming94 Questions
Exam 21: The Modi and Vam Methods of Solving Transportation Problems135 Questions
Exam 22: Vehicle Routing and Scheduling111 Questions
Exam 23 Managing Quality155 Questions
Exam 24: Process Strategy107 Questions
Exam 25: Supply-Chain Management73 Questions
Exam 26: Vehicle Routing and Scheduling92 Questions
Select questions type
Daily demand is half of daily production. If setup and holding costs are equal, determine how Q and D are related.
(Essay)
4.8/5
(39)
A kanban system requires little variability in lead time because shortages have their impact on the entire productive system.
(True/False)
4.7/5
(30)
Which of the following statements regarding a pull system is true?
(Multiple Choice)
4.8/5
(34)
The 5Ss-sort/segregate, simplify/straighten, shine/sweep, standardize, and sustain/self discipline-are important to lean production because they act as a means to reduce waste.
(True/False)
4.8/5
(32)
Reduction of in-transit inventory can be encouraged through use of
(Multiple Choice)
4.9/5
(36)
Which one of the following is a concern expressed by suppliers?
(Multiple Choice)
4.9/5
(31)
Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management wants to use 10 kanbans how many computers should each one hold?
(Multiple Choice)
4.9/5
(35)
Which one of the following is not a requirement of JIT systems?
(Multiple Choice)
4.9/5
(36)
A push system means providing the next station with exactly what is needed when it is needed.
(True/False)
4.8/5
(25)
Customer demand will always remain an unknown, so it is not considered a source of variation.
(True/False)
4.8/5
(33)
If setup times and costs can be reduced enough, the JIT ideal of "Lot Size = 1" can be achieved.
(True/False)
4.9/5
(34)
If the goals of JIT partnerships are met, which of the following is a result?
(Multiple Choice)
4.9/5
(32)
Inventory has only one positive aspect, which is availability; inventory has several negatives, including increased material handling, obsolescence, and damage.
(True/False)
4.7/5
(40)
Which of the following statements regarding JIT in services is true?
(Multiple Choice)
4.9/5
(30)
Which of the following is an illustration of employee empowerment?
(Multiple Choice)
4.7/5
(39)
Waste is anything that does not add value, such as storage or inspection of items; waste also includes any activity that does not add value from the consumer's perspective.
(True/False)
4.7/5
(40)