Exam 15: Short-Term Scheduling
Exam 1: Operations and Productivity127 Questions
Exam 2: Operations Strategy in a Global Environment119 Questions
Exam 3: Project Management120 Questions
Exam 4: Forecasting141 Questions
Exam 5: Design of Goods and Services118 Questions
Exam 6: Managing Quality127 Questions
Exam 7: Process Strategy108 Questions
Exam 8: Location Strategies120 Questions
Exam 9: Layout Strategies145 Questions
Exam 10: Human Resources,job Design,and Work Measurement154 Questions
Exam 11: Supply Chain Management145 Questions
Exam 12: Inventory Management163 Questions
Exam 13: Aggregate Planning and Sop116 Questions
Exam 14: Material Requirements Planning Mrpand Erp116 Questions
Exam 15: Short-Term Scheduling115 Questions
Exam 16: Jit,tps,and Lean Operations115 Questions
Exam 17: Maintenance and Reliability111 Questions
Exam 18: Sustainability in the Supply Chain80 Questions
Exam 19: Statistical Process Control144 Questions
Exam 20: Capacity and Constraint Management96 Questions
Exam 21: Supply Chain Management Analytics55 Questions
Exam 22: Decision-Making Tools96 Questions
Exam 23: Linear Programming88 Questions
Exam 24: Transportation Models89 Questions
Exam 25: Waiting-Line Models119 Questions
Exam 26: Learning Curves110 Questions
Exam 27: Simulation74 Questions
Select questions type
A work center had planned outputs of 10,15,13,and 20 hours with actual outputs of 12,14,13,and 18 hours.What is the cumulative deviation in output?
Free
(Multiple Choice)
4.9/5
(30)
Correct Answer:
C
In services,the scheduling emphasis is usually on staffing levels,not materials.
Free
(True/False)
4.8/5
(41)
Correct Answer:
True
Scheduling optimization systems used in retail stores typically track customer traffic in 4-hour time increments.
Free
(True/False)
4.9/5
(29)
Correct Answer:
False
Jack's Refrigeration Repair is under contract to repair,recondition,and/or refurbish commercial and industrial icemakers from restaurants,seafood processors,and similar organizations.Jack currently has five jobs to be scheduled,shown in the order in which they arrived.
(a)Complete the following table.(Show your supporting calculations below).
(b)Which dispatching rule has the best score for flow time?
(c)Which dispatching rule has the best score for work-in-process (jobs in the system)?
(d)Which dispatching rule has the best score for lateness?



(Essay)
4.8/5
(35)
What does the use of the shortest processing time sequencing rule generally produce?
(Multiple Choice)
4.9/5
(27)
Bob Dresser operates a major appliance warranty service center.His operation has two check stations that are required at the end of every repair task performed by his appliance repair staff.These are the Functionality Review (FR)and the Overall Scan (OS).The FR must be performed successfully before the OS is begun.On Friday morning,six repair jobs are completed,awaiting these two inspection activities.Processing times are given in minutes.
a.What is the optimal sequence of jobs for the objective of minimizing the total flow time?
b.Show your work,and document the sequence.
c.Chart the solution to this problem.
d.What jobs are being processed at time period 90?
e.What is the total flow time of this problem?



(Essay)
4.7/5
(35)
The following jobs are waiting to be processed at your work center,which cleans valve body castings.Job numbers are assigned sequentially upon arrival in the facility (a missing number means that job does not require your work center).All dates are specified as days from today.
a.In what sequence should the jobs be processed according to the FCFS scheduling rule?
b.In what sequence should the jobs be processed according to the EDD scheduling rule?
c.In what sequence should the jobs be processed according to the SPT scheduling rule?
d.In what sequence should the jobs be processed according to the LPT scheduling rule?
e.In what sequence should the jobs be processed according to the critical ratio scheduling rule?

(Essay)
4.8/5
(27)
Which of the following statements regarding scheduling at Delta Airlines is FALSE?
(Multiple Choice)
4.8/5
(43)
With forward scheduling,jobs are scheduled as late as possible within the time allowed by the customer due dates.
(True/False)
4.8/5
(32)
Which of the following is an aid used to monitor jobs in progress?
(Multiple Choice)
4.8/5
(32)
A recent advance in short-term scheduling that makes use of expert systems and simulation in solving dynamic scheduling problems is:
(Multiple Choice)
4.7/5
(31)
The ________ is a special class of linear programming models that involves assigning tasks or jobs to resources.
(Essay)
4.9/5
(34)
A firm that specializes in desktop publishing for local charities has agreed to take on the following jobs.The firm has not decided which dispatching rule to apply in order to prioritize the jobs and fix them into the schedule.All dates are specified as days from today.
a.Complete the following table.Show your supporting calculations below.
b.Which dispatching rule has the best score for flow time?
c.Which dispatching rule has the best score for work-in-process (jobs in the system)?
d.Which dispatching rule has the best score for lateness?



(Essay)
4.9/5
(28)
Johnson's rule sequences a set of jobs through two different machines or work centers in the same order.
(True/False)
4.8/5
(29)
What is the difference between a Gantt load chart and a Gantt scheduling chart?
(Essay)
4.9/5
(31)