Exam 3: Project Management
Exam 1: Operations and Productivity127 Questions
Exam 2: Operations Strategy in a Global Environment119 Questions
Exam 3: Project Management120 Questions
Exam 4: Forecasting141 Questions
Exam 5: Design of Goods and Services118 Questions
Exam 6: Managing Quality127 Questions
Exam 7: Process Strategy108 Questions
Exam 8: Location Strategies120 Questions
Exam 9: Layout Strategies145 Questions
Exam 10: Human Resources,job Design,and Work Measurement154 Questions
Exam 11: Supply Chain Management145 Questions
Exam 12: Inventory Management163 Questions
Exam 13: Aggregate Planning and Sop116 Questions
Exam 14: Material Requirements Planning Mrpand Erp116 Questions
Exam 15: Short-Term Scheduling115 Questions
Exam 16: Jit,tps,and Lean Operations115 Questions
Exam 17: Maintenance and Reliability111 Questions
Exam 18: Sustainability in the Supply Chain80 Questions
Exam 19: Statistical Process Control144 Questions
Exam 20: Capacity and Constraint Management96 Questions
Exam 21: Supply Chain Management Analytics55 Questions
Exam 22: Decision-Making Tools96 Questions
Exam 23: Linear Programming88 Questions
Exam 24: Transportation Models89 Questions
Exam 25: Waiting-Line Models119 Questions
Exam 26: Learning Curves110 Questions
Exam 27: Simulation74 Questions
Select questions type
A combination of effective Gantt chart use and other tactics allowed Delta to cut the average time for a plane layover by what % of the original 60 minute duration?
Free
(Multiple Choice)
4.9/5
(35)
Correct Answer:
A
The beta distribution is used in project management to:
Free
(Multiple Choice)
4.7/5
(31)
Correct Answer:
E
A network consists of the activities in the following list.Times are given in weeks.
a.Draw the network diagram.
b.Calculate the ES,EF,LS,LF,and Slack for each activity.
c.What is project completion time?

Free
(Essay)
4.8/5
(36)
Correct Answer:
(a) (b,c)
Ethical issues that may arise in projects large and small include:
(Multiple Choice)
4.8/5
(35)
A simple CPM network has three activities,A,B,and C.A is an immediate predecessor of B and of C.B is an immediate predecessor of C.The activity durations are A=4,B=3,C=8.
(Multiple Choice)
4.9/5
(38)
Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project.Given the project table below calculate the crash cost for 8 hours of time-savings.Suppose Pirmin calls the customer and asks for a project extension,reducing the amount of time he needs to crash.Calculate both the maximum time-savings available on a $25 crash budget and the cost to crash four hours of savings.


(Essay)
4.9/5
(32)
Which of the following statements regarding PERT times is true?
(Multiple Choice)
4.8/5
(38)
Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
a.What is the crash cost per unit time for each of the three activities?
b.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost?
c.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost?

(Essay)
4.9/5
(39)
What are the three phases of a project? Describe each in a sentence or two.
(Essay)
4.9/5
(44)
The time an activity will take assuming very unfavorable conditions is:
(Multiple Choice)
4.7/5
(36)
A contractor's project being analyzed by PERT has an estimated time for the critical path of 120 days.The sum of all activity variances is 81;the sum of variances along the critical path is 64.What is the probability that the project will take 130 or more days to complete?
(Multiple Choice)
4.9/5
(29)
In project management,crashing an activity must consider the impact on all paths in the network.
(True/False)
4.8/5
(37)
Ethical issues that can arise in projects include gifts from contractors,pressure to mask delays with false status reports,and pressure to compromise project quality to meet bonuses or avoid penalties related to schedules.
(True/False)
4.8/5
(33)
A project manager is interested in crashing a project with variable activity times.Which of the following tools should he/she employ?
(Multiple Choice)
4.9/5
(36)
Work breakdown structure is a useful tool in project management because it addresses the timing of individual work elements.
(True/False)
4.9/5
(32)