Exam 5: Estimating Project Times and Costs
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection101 Questions
Exam 3: Organization: Structure and Culture102 Questions
Exam 4: Defining the Project112 Questions
Exam 5: Estimating Project Times and Costs95 Questions
Exam 6: Developing a Project Schedule128 Questions
Exam 7: Managing Risk105 Questions
Exam 8: Scheduling Resources and Costs114 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager98 Questions
Exam 11: Managing Project Teams103 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations102 Questions
Exam 13: Progress and Performance Measurement and Evaluation98 Questions
Exam 14: Project Closure97 Questions
Exam 15: Agile Project Management94 Questions
Exam 16: International Projects103 Questions
Select questions type
When work package estimates are made by individuals most knowledgeable about the work being performed and these estimates are then "rolled up" to find estimated costs for major deliverables and the project itself, ____________ estimating is being used.
(Multiple Choice)
4.9/5
(36)
Which of the following would best represent direct project costs?
(Multiple Choice)
4.8/5
(34)
Identify and briefly describe three out of the six factors that should be considered to improve the quality of estimates for project times and costs.
(Short Answer)
4.8/5
(45)
Repetition of a task generally results in a reduction of labor hours each successive time a worker performs that task.
(Multiple Choice)
4.7/5
(40)
Identify the drawbacks to an excessive detail in estimating project times and costs.
(Essay)
4.9/5
(38)
The consensus method of estimating costs is a bottom-up technique.
(True/False)
4.8/5
(47)
Which of the following does NOT help describe a bottom-up estimating approach?
(Multiple Choice)
4.9/5
(30)
Top-down estimates usually are derived from someone who uses experience and / or information to determine the project duration and total cost.
(True/False)
4.8/5
(39)
Describe phase estimating. When should it be used and how is it different from all other top-down and bottom-up methods of estimating?
(Essay)
5.0/5
(32)
The salary of the project manager and her administrative assistant are classified as direct labor costs.
(True/False)
4.8/5
(44)
List and briefly describe four reasons why estimating time and cost are important to project management.
(Essay)
4.9/5
(39)
Work package estimates should include allowances for contingencies.
(True/False)
4.9/5
(30)
Which of the following is a good condition for top-down estimating?
(Multiple Choice)
4.7/5
(38)
Refining estimates may be necessary for a number of reasons. For example, people working on prototype development needing time to interact with the design engineers after the design is completed is a good example of
(Multiple Choice)
4.7/5
(39)
A project leader is forecasting how much money his department needs to support a new project. He estimates that two people and $25,000 in expenses will cover his needs. Because management typically insists on reducing forecasts by 20 percent, he increases his estimates to allow for that reduction. Which of the following factors is illustrated in this situation?
(Multiple Choice)
4.8/5
(22)
Refining Estimates may be necessary for a number of reasons. For example, a manager getting further into a project and obtaining a better understanding of what needs to be done to accomplish a project and meet the needs of the customer is an example of
(Multiple Choice)
4.8/5
(38)
Large projects that have long time horizons and a very high complexity can be referred to as
(Multiple Choice)
4.8/5
(41)
Companies are using which of the following for improving the estimating process for future projects?
(Multiple Choice)
4.8/5
(33)
Showing 41 - 60 of 95
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)