Exam 21: Master Scheduling and Material Requirements Planning
Exam 1: Introduction to Managing Global Operations and Supply Chains97 Questions
Exam 2: Operations and Supply Chain Strategies99 Questions
Exam 3: Project Management100 Questions
Exam 4: Supplement: Project Management100 Questions
Exam 5: Product and Service Innovations100 Questions
Exam 6: Supplement: Reliability98 Questions
Exam 7: Managing for Quality100 Questions
Exam 8: Quality Improvement and Control Tools100 Questions
Exam 9: Capacity Planning100 Questions
Exam 10: Supply Chain Design and Location Planning100 Questions
Exam 11: Process Design and Layout Planning100 Questions
Exam 12: Supplement: Tools for Analyzing, Designing, and Selecting Processes and Layouts99 Questions
Exam 13: Supplier Management100 Questions
Exam 14: Logistics Management100 Questions
Exam 15: Demand Management and Customer Service100 Questions
Exam 16: Demand Forecasting Methods100 Questions
Exam 17: Lean Operations and Supply Chains99 Questions
Exam 18: Inventory Management100 Questions
Exam 19: Inventory Control Models100 Questions
Exam 20: Sales and Operations Planning99 Questions
Exam 21: Master Scheduling and Material Requirements Planning100 Questions
Exam 22: Supplement: Capacity Requirements Planning, MRP II, ERP, and DRP100 Questions
Exam 23: Detailed Scheduling100 Questions
Exam 24: Linear Programming100 Questions
Exam 25: The Transportation Models100 Questions
Exam 26: Waiting Line Models100 Questions
Exam 27: Simulation100 Questions
Exam 28: Learning Curves99 Questions
Exam 29: Decision-Making Tools100 Questions
Select questions type
Parent Item A requires two units of Item B and three units of Item C.Upon production of 500 units of Item A,it was calculated that 1,000 units of Item B were used in the production process.This an example of ______.
(Multiple Choice)
4.7/5
(33)
The output of individual production quantities of the end items to be produced at various points of the short-term planning horizon is called ______.
(Multiple Choice)
4.9/5
(30)
A standard quantity issued to the production process is called ______.
(Multiple Choice)
4.7/5
(37)
The effectiveness of a master schedule depends on the ______.
(Multiple Choice)
4.9/5
(36)
The time between placing an order and receiving the item is called ______.
(Multiple Choice)
4.9/5
(40)
The leftover inventory from previous periods that is available at the start of a period is called ______.
(Multiple Choice)
4.8/5
(36)
The process of updating the master schedule and moving from one period to the next is called ______.
(Multiple Choice)
4.7/5
(35)
Which file contains data about materials,components,parts,and the assembling sequence of an end item?
(Multiple Choice)
4.9/5
(36)
The amount of a particular item ordered from a supplier is called the ______.
(Multiple Choice)
4.8/5
(36)
To minimize the effects of uncertainty due to lead times,MRP systems incorporate ______.
(Multiple Choice)
4.8/5
(41)
Which of the following is relevant to operations and supply chain management?
(Multiple Choice)
4.8/5
(35)
MRP systems ensure that materials and components are available ______.
(Multiple Choice)
4.9/5
(31)
Changes in which phase of the MPS will be the least disruptive?
(Multiple Choice)
4.8/5
(36)
In an ATO production environment,which process is used to assemble modules and subassemblies into final product?
(Multiple Choice)
4.9/5
(30)
Showing 81 - 100 of 100