Exam 5: Estimating Project Times and Costs
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection88 Questions
Exam 3: Organization: Structure and Culture94 Questions
Exam 4: Defining the Project89 Questions
Exam 5: Estimating Project Times and Costs91 Questions
Exam 6: Developing a Project Plan94 Questions
Exam 7: Managing Risk87 Questions
Exam 8: Scheduling Resources and Costs90 Questions
Exam 9: Reducing Project Duration94 Questions
Exam 10: Leadership: Being an Effective Project Manager88 Questions
Exam 11: Managing Project Teams94 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations94 Questions
Exam 13: Progress and Performance Measurement and Evaluation88 Questions
Exam 14: Project Closure88 Questions
Exam 15: International Projects94 Questions
Exam 16: Oversight86 Questions
Exam 17: An Introduction to Agile Project Management85 Questions
Exam 18: Project Management Career Paths35 Questions
Select questions type
Which of the follow top-down methods is used when projects closely follow past projects in features and costs and result in costs being assigned by percentages to major segments of the project?
(Multiple Choice)
4.9/5
(34)
Project costs such as labor and materials are typically classified as ________ costs.
(Short Answer)
4.8/5
(36)
Estimates should be made based on ________ conditions, efficient methods, and a normal level of resources.
(Short Answer)
4.8/5
(31)
Due to the averaging out of under-estimates and over-estimates, a long duration project is more likely to be on target than a short term, small project.
(True/False)
4.8/5
(42)
The project structure chosen to manage the project will have little impact on the actual project work to be accomplished.
(True/False)
4.8/5
(32)
The cost to prepare a top-down budget will typically run ________ percent of the total project cost.
(Short Answer)
4.7/5
(41)
Which of the following is a good condition for top-down estimating?
(Multiple Choice)
4.8/5
(42)
The process of forecasting or approximating the time and cost of completing project deliverables is called
(Multiple Choice)
5.0/5
(36)
Learning curves are more likely to apply in situations where most of the costs are
(Multiple Choice)
4.8/5
(42)
The __________ method is a top-down approach that uses the pooled experience of senior and/or middle managers to estimate the total project duration and cost.
(Short Answer)
4.8/5
(24)
In practice, estimating processes are frequently classified as
(Multiple Choice)
4.9/5
(43)
Showing 81 - 91 of 91
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)