Exam 7: The Project Schedule and Budget

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

What is a baseline plan?

(Essay)
4.8/5
(35)

A start-to-finish activity is the most common relationship between two activities.

(True/False)
4.8/5
(41)

Under the Precedence Diagramming Method,the most common relationship between two activities which implies a logical sequence is called:

(Multiple Choice)
4.9/5
(37)

Define predecessor,successor,and parallel activities.Give a real world example of each.

(Essay)
4.7/5
(35)

Why do many people inflate their estimates?

(Essay)
4.9/5
(34)

The direct costs of using a resource is the only type of cost that should be considered when developing the project budget.

(True/False)
4.8/5
(41)

Why should assumptions used in estimating be documented?

(Essay)
4.9/5
(30)

The technique used to help manage the Polaris submarine project and which bases activity estimates on probabilistic estimates of three scenarios is most closely associated with:

(Multiple Choice)
4.8/5
(44)

Why should the project manager ensure that the project resources are leveled?

(Essay)
4.8/5
(39)

Completing activities in parallel is called_____

(Multiple Choice)
4.7/5
(38)

PERT was developed in the 1950s to create a visual representation of scheduled activities,their logical sequence,and interrelationships using a statistical probability distribution.

(True/False)
4.8/5
(39)

The critical path is the shortest path in the project network and also is the longest time in which the project can be completed.

(True/False)
4.8/5
(37)

_____ is well suited for developing simulations where the project manager can conduct sensitivity analysis for schedule planning and risk analysis.

(Multiple Choice)
4.8/5
(37)

Time and effort needed to gather experience on a technology or process are _____

(Multiple Choice)
4.9/5
(39)

An over allocated resource would arise when Mary is assigned to work on two tasks scheduled at the same time.

(True/False)
4.8/5
(34)

The Critical Path is:

(Multiple Choice)
4.9/5
(30)

To make a decision to attempt to build an application system based on what was left after a previous attempt ended in failure primarily because of the large investment the company made in the failed project most likely was made by a manager who did not fully understand:

(Multiple Choice)
4.9/5
(31)

_____is ensuring that project resources are not overallocated.

(Multiple Choice)
4.9/5
(34)

The idea that there is a cost associated with using a resource is _____

(Multiple Choice)
4.7/5
(38)

The project budget is determined by the project schedule,the cost of the resources assigned to each of the tasks,and by any other direct or indirect costs and reserves.

(True/False)
4.8/5
(38)
Showing 41 - 60 of 64
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)