Exam 7: The Project Schedule and Budget
Exam 1: The Nature of Information Technology Projects56 Questions
Exam 2: Initializing and Conceptualizing the IT Project63 Questions
Exam 3: The Project Infrastructure61 Questions
Exam 4: The Human Side of Project Management53 Questions
Exam 5: Defining and Managing Project and Product Scope49 Questions
Exam 6: The Work Breakdown Structure and Project Estimation66 Questions
Exam 7: The Project Schedule and Budget64 Questions
Exam 8: Managing Project Risk69 Questions
Exam 9: Project Communication,tracking,and Reporting63 Questions
Exam 10: It Project Quality Management71 Questions
Exam 11: Managing Organizational Change, resistance, and Conflict81 Questions
Exam 12: Project Procurement Management and Outsourcing73 Questions
Exam 13: Leadership and Ethics75 Questions
Exam 14: Project Implementation, closure, and Evaluation65 Questions
Select questions type
An activity being analyzed under PERT was judged to most likely have a duration of 40 days.When considering the time it would take to complete the activity if every relevant factor went well,it was estimated to be able to be doable in 20 days and even under the worst case imaginable,the task would be take 50 days.The estimates PERT duration of that activity is:
(Multiple Choice)
4.9/5
(36)
Waiting to leave your shift until another person shows up is an example of:
(Multiple Choice)
4.9/5
(38)
What is the difference between crashing and fast tracking a project's schedule?
(Essay)
4.9/5
(37)
The critical path is the longest path in the project network and also is the shortest time in which the project can be completed.
(True/False)
4.8/5
(37)
Identifying the critical path is important because any change in the duration of the activities or tasks on the critical path will affect the project's schedule.
(True/False)
4.8/5
(34)
In the context of critical chain project management,what is resource contention?
(Essay)
4.8/5
(37)
Sunk costs include such things as rent,utilities,insurance,and other administrative costs.
(True/False)
4.9/5
(35)
Under the Precedence Diagramming Method,the least common relationship between two activities which occurs when they must complete at the same time is called:
(Multiple Choice)
4.8/5
(31)
How can parallel activities help shorten the project schedule? Are there any trade-offs?
(Essay)
4.7/5
(40)
Rent,utilities,insurance and administrative costs are examples of:
(Multiple Choice)
4.8/5
(33)
Starting the next task before the first task is complete is _____
(Multiple Choice)
4.9/5
(45)
The tool most closely associated with activity bars across a horizontal time axis is:
(Multiple Choice)
4.9/5
(30)
Project network diagrams provide valuable information about the logical sequence and dependencies among the various activities and tasks so that a completion date or deadline can be determined.
(True/False)
4.7/5
(42)
Define the following and give a real world example of each other than the ones described in this book): Finish-to-Start;Start-to-Start;Finish-to-Finish;Start-to-Finish.
(Essay)
4.8/5
(38)
Adding resources to an activity to shorten the critical path is called_____
(Multiple Choice)
4.8/5
(38)
_____ can help manage the Critical Path by providing information about which activities can be delayed without affecting the deadline target date.
(Multiple Choice)
4.8/5
(36)
_____ provide valuable information about the logical sequence and dependencies among the various activities and tasks:
(Multiple Choice)
4.9/5
(30)
Predecessor activities are activities that can be worked on at the same time as another activity.
(True/False)
4.8/5
(46)
Showing 21 - 40 of 64
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)