Gantt charts give a timeline for each of a project's activities,but they do not adequately illustrate the interrelationships between the activities and the resources.

Free
(True/False)
4.8/5
(34)
Correct Answer:
Verified

True

________ is a network technique using only one time factor per activity that enables managers to schedule,monitor,and control large and complex projects.

Free
(Essay)
4.7/5
(41)
Correct Answer:
Verified

Critical path method or CPM

Which of the following statements regarding EllisDon is false?

Free
(Multiple Choice)
4.8/5
(32)
Correct Answer:
Verified

D

Describe in words how to calculate a project's standard deviation.What assumption allows that calculation to be accurate?

(Essay)
4.9/5
(35)

Describe some of the challenges faced in the construction of the new 11-story building at Arnold Palmer Hospital in Orlando,Florida.

(Essay)
4.9/5
(30)

If an activity whose normal duration is 55 days can be shortened to 50 days for an added cost of $45,000,the crash cost per period is

(Multiple Choice)
4.8/5
(22)

Draw the AOA and AON networks for the following project and calculate the minimum project duration. Draw the AOA and AON networks for the following project and calculate the minimum project duration.

(Essay)
4.9/5
(32)

An activity on a PERT network has these time estimates: optimistic = 1,most likely = 2,and pessimistic = 5.Its expected time is

(Multiple Choice)
4.8/5
(36)

The project organization works best when which of the following conditions are satisfied?

(Multiple Choice)
4.9/5
(39)

The ________ distribution is used by PERT analysis to calculate expected activity times and variances.

(Multiple Choice)
4.9/5
(41)

The ________ distribution is appropriate for calculating expected activity times and activity variances in PERT networks.

(Essay)
4.9/5
(35)

The critical path can be determined by use of either the "forward pass" or the "backward pass."

(True/False)
4.8/5
(47)

Explain why the critical path is the longest,not the shortest,path through a network.

(Essay)
4.8/5
(39)

The phases of project management are

(Multiple Choice)
4.8/5
(36)

What are some of the ethical issues faced by project managers? Which of these are likely to occur before a project begins,which are likely to occur while the project is underway,and which may occur after a project is complete? Illustrate any one of these from recent news.

(Essay)
4.9/5
(35)

Briefly discuss what is meant by critical path analysis.What are critical path activities and why are they important?

(Essay)
5.0/5
(29)

Which of the following statements regarding PERT times is true?

(Multiple Choice)
4.8/5
(30)

The fundamental difference between PERT and CPM is that PERT uses the beta distribution for crashing projects while CPM uses cost estimates.

(True/False)
4.8/5
(43)

What is the basic difference between PERT and CPM?

(Essay)
4.9/5
(33)

Which of the following statements regarding critical paths is true?

(Multiple Choice)
4.9/5
(37)