Exam 14: Material Requirements Planning Mrpand ERP
Exam 1: Operations and Productivity129 Questions
Exam 2: Operations Strategy in a Global Environment120 Questions
Exam 3: Project Management124 Questions
Exam 4: Forecasting141 Questions
Exam 5: Design of Goods and Services121 Questions
Exam 6: Managing Quality125 Questions
Exam 7: Process Strategy113 Questions
Exam 8: Location Strategies121 Questions
Exam 9: Layout Strategies146 Questions
Exam 10: Human Resources,job Design,and Work Measurement159 Questions
Exam 11: Supply Chain Management145 Questions
Exam 12: Inventory Management165 Questions
Exam 13: Aggregate Planning and Sop116 Questions
Exam 14: Material Requirements Planning Mrpand ERP113 Questions
Exam 15: Short-Term Scheduling116 Questions
Exam 16: Lean Operations116 Questions
Exam 17: Maintenance and Reliability114 Questions
Exam 18: Sustainability in the Supply Chain84 Questions
Exam 19: Statistical Process Control144 Questions
Exam 20: Capacity and Constraint Management101 Questions
Exam 21: Supply Chain Management Analytics67 Questions
Exam 22: Decision-Making Tools100 Questions
Exam 23: Linear Programming98 Questions
Exam 24: Transportation Models89 Questions
Exam 25: Waiting-Line Models119 Questions
Exam 26: Learning Curves110 Questions
Exam 27: Simulation75 Questions
Select questions type
Effective use of MRP and other dependent demand models does not require which of the following?
Free
(Multiple Choice)
4.9/5
(36)
Correct Answer:
E
What is the process of tracing upward in the bill of material from the component to the parent item in order to determine the cause for the component requirement?
Free
(Multiple Choice)
4.8/5
(40)
Correct Answer:
C
________ are a way of allowing a segment of the master schedule to be designated as "not to be rescheduled."
Free
(Essay)
4.8/5
(31)
Correct Answer:
Time fences
Time fences divide that segment of the master schedule that can be revised from that section that is "not to be rescheduled."
(True/False)
4.9/5
(34)
Planning bills of material are bills of material for "kits" of inexpensive items such as washers,nuts,and bolts.
(True/False)
4.7/5
(44)
Consider the following requirements for a certain product.
Beginning inventory = 500 units
Setup cost = $500 per setup
Lead time = 1 week
Holding cost = $3 per unit per week
a.Develop the lot-for-lot MRP table.
b.Calculate the total relevant costs.

(Essay)
4.7/5
(28)
Explain the difference between a gross requirements plan and a net requirements plan.
(Essay)
4.7/5
(34)
It is week 1 and there are currently 20 As in stock.We need 300 As at the start of week 5.If there are scheduled receipts planned for week 3 and week 4 of 120 As each and A has a lead time of 1 week,when and how large of an order should be placed to meet the requirement of 300 As?
(Multiple Choice)
4.7/5
(34)
An order for 110 units of Product M has been placed.There are currently 30 units of Product M on hand.Each M requires 4 units of Component N.There are 20 units of N on hand.What are the net requirements for N?
(Multiple Choice)
4.9/5
(36)
________ is a lot-sizing technique that generates exactly what is required to meet the plan.
(Essay)
4.8/5
(41)
A very simple product (A)consists of a base (B)and a casting (C).The base consists of a plate (P)and three fasteners (F).There are currently 30 castings and 100 bases on hand.Final assembly takes one week.The casting has a lead time of three weeks.All other parts have one-week lead times.There are no scheduled receipts.All components use the lot-for-lot technique.The master schedule requires 80 units of product A in week 5 and 120 in week 8.Produce the MRP for the upcoming eight weeks.Produce a list of all planned order releases.
(Essay)
4.7/5
(35)
Wheeled Coach uses ________ as the catalyst for low inventory,high quality,tight schedules,and accurate records.
(Essay)
4.8/5
(31)
A(n)________ can illustrate whether a work center has been scheduled beyond its capacity.
(Essay)
4.8/5
(28)
Jacquie Welkener,operations manager for ABC Technologies,must schedule work for the next five days.Each unit takes 30 minutes to process.Available capacity is 8 hours per day.The production order quantities are 12,18,20,13,and 17 for Monday through Friday,respectively.What should be the production plan?
(Essay)
4.8/5
(31)
If a load report (resource requirements profile)shows a work center scheduled beyond capacity:
(Multiple Choice)
4.7/5
(28)
A grill assembly takes 20 washers.Instead of listing these washers separately,they are grouped into a single kit for production.How is the bill of material for the washers classified?
(Multiple Choice)
4.9/5
(31)
A(n)________ is a bill of material for components,usually subassemblies,that exist only temporarily;they are never inventoried.
(Essay)
5.0/5
(29)
If 100 units of Q are needed and 10 are already in stock,then the gross requirement is 100 and the net requirement is 90.
(True/False)
4.8/5
(37)
Showing 1 - 20 of 113
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)