Exam 3: Project Management
Exam 1: Operations and Productivity129 Questions
Exam 2: Operations Strategy in a Global Environment120 Questions
Exam 3: Project Management124 Questions
Exam 4: Forecasting141 Questions
Exam 5: Design of Goods and Services121 Questions
Exam 6: Managing Quality125 Questions
Exam 7: Process Strategy113 Questions
Exam 8: Location Strategies121 Questions
Exam 9: Layout Strategies146 Questions
Exam 10: Human Resources,job Design,and Work Measurement159 Questions
Exam 11: Supply Chain Management145 Questions
Exam 12: Inventory Management165 Questions
Exam 13: Aggregate Planning and Sop116 Questions
Exam 14: Material Requirements Planning Mrpand ERP113 Questions
Exam 15: Short-Term Scheduling116 Questions
Exam 16: Lean Operations116 Questions
Exam 17: Maintenance and Reliability114 Questions
Exam 18: Sustainability in the Supply Chain84 Questions
Exam 19: Statistical Process Control144 Questions
Exam 20: Capacity and Constraint Management101 Questions
Exam 21: Supply Chain Management Analytics67 Questions
Exam 22: Decision-Making Tools100 Questions
Exam 23: Linear Programming98 Questions
Exam 24: Transportation Models89 Questions
Exam 25: Waiting-Line Models119 Questions
Exam 26: Learning Curves110 Questions
Exam 27: Simulation75 Questions
Select questions type
What is a project organization?
Free
(Essay)
4.8/5
(33)
Correct Answer:
A project organization is an organization formed to ensure that programs (projects)receive the proper management and attention.
The network below represents a project being analyzed by the critical path method.Activity durations are A = 5,B = 2,C = 12,D = 3,E = 5,F = 1,G = 7,H = 2,I = 10,and J = 6.
a.What task must be on the critical path,regardless of activity durations?
b.What is the duration of path A-B-E-H-J?
c.What is the critical path of this network?
d.What is the length of the critical path?
e.What is slack time at activity H?
f.What is the Late Finish of activity H?
g.If activity C were delayed by two time units,what would happen to the project duration?

Free
(Essay)
4.8/5
(31)
Correct Answer:
(a)J; (b)20; (c)A-B-G-I-J; (d)30; (e)5; (f)24; (g)no impact.
Match the following steps in Microsoft's development of Windows 8 to their respective WBS level. Step Level
Develop Windows 8 Operating System ?
System Testing ?
Compatible with Windows 7 ?
Develop GUI's ?
Module Testing ?
Free
(Multiple Choice)
4.8/5
(39)
Correct Answer:
A
Draw the AOA and AON networks for the following project and calculate the minimum project duration.


(Essay)
4.9/5
(35)
An activity on a PERT network has these time estimates: optimistic = 2,most likely = 3,and pessimistic = 8.What is its expected activity time and variance?
(Multiple Choice)
4.7/5
(32)
Describe some of the challenges faced in the construction of the new 11-story building at Arnold Palmer Hospital in Orlando,Florida.
(Essay)
4.7/5
(38)
A contractor's project being analyzed by PERT has an estimated time for the critical path of 120 days.The sum of all activity variances is 81;the sum of variances along the critical path is 64.What is the probability that the project will take 130 or more days to complete?
(Multiple Choice)
4.8/5
(40)
________ is decreasing activity time in a network to reduce time on the critical path so total completion time is reduced.
(Essay)
4.8/5
(37)
If an activity whose normal duration is 13 days can be shortened to 10 days for an added cost of $1,500,what is the crash cost per period?
(Multiple Choice)
4.9/5
(40)
The standard deviation of project duration is the average of the standard deviation of all activities on the critical path.
(True/False)
4.9/5
(30)
A project organization that becomes permanent is often referred to as a:
(Multiple Choice)
4.9/5
(44)
Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
a.What is the crash cost per unit time for activity A?
b.What is the crash cost per unit time for activity B?
c.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost?
d.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost?
e.Assuming no other paths become critical,how much can this project be shortened at what total added cost?

(Essay)
4.8/5
(32)
________ is the amount of time an individual activity in a network can be delayed without delaying the entire project.
(Essay)
4.7/5
(40)
A project organization works best for an organization when the project resides in only one of its functional areas.
(True/False)
4.8/5
(36)
The critical path for the network activities shown below is ________ with duration ________. 

(Multiple Choice)
4.8/5
(35)
Showing 1 - 20 of 124
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)