Exam 15: Scheduling for the Short-Term
Exam 1: Operations and Productivity127 Questions
Exam 2: The Global Environment and Operations Strategy119 Questions
Exam 3: Managing Projects120 Questions
Exam 4: Forecasting Demand140 Questions
Exam 5: Product Design118 Questions
Exam 6: Quality Management and International Standards123 Questions
Exam 7: Process Design108 Questions
Exam 8: Location Decisions121 Questions
Exam 9: Layout Decisions146 Questions
Exam 10: Job Design and Work Measurement154 Questions
Exam 11: Supply Chain Management145 Questions
Exam 12: Managing Inventory163 Questions
Exam 13: Aggregate Scheduling116 Questions
Exam 14: Material Requirements Planning Mrpand Erp113 Questions
Exam 15: Scheduling for the Short-Term116 Questions
Exam 16: Jit,lean Operations,and the Toyota Production System115 Questions
Exam 17: Maintenance and Reliability Decisions111 Questions
Exam 18: Sustainability80 Questions
Exam 19: Statistical Process Control144 Questions
Exam 20: Capacity Planning96 Questions
Exam 21: Supply Chain Modeling55 Questions
Exam 22: Decision Modeling97 Questions
Exam 23: Linear Programming Models88 Questions
Exam 24: Transportation Modeling89 Questions
Exam 25: Queuing Models119 Questions
Exam 26: Learning Curves110 Questions
Exam 27: Modeling with Simulation75 Questions
Select questions type
________ are planning charts used to schedule resources and allocate time.
(Essay)
4.7/5
(41)
A work center had actual input of 280 hours and actual output of 270 hours.What is the change in backlog?
(Multiple Choice)
4.7/5
(41)
Which of the following is an aid used to monitor jobs in progress?
(Multiple Choice)
4.8/5
(33)
Which critical ratio value implies that a job is already late?
(Multiple Choice)
4.8/5
(32)
________ cards are used to control the amount of work in a work center,aiding input-output control.
(Essay)
4.8/5
(34)
Which of the following dispatching rules tends to minimize job flow time?
(Multiple Choice)
4.9/5
(36)
________ determine the sequence of jobs in process-oriented facilities.
(Essay)
4.8/5
(42)
Use Johnson's rule to determine the optimal sequencing for the five jobs to be processed on two machines in a fixed order (Machine 1 before Machine 2).The processing times in hours are given in the table below.
a.What is the optimal sequence?
b.What is the total flow time for this sequence?


(Essay)
4.9/5
(37)
The correct sequence from longest to smallest duration scheduling is:
(Multiple Choice)
4.8/5
(37)
At Morgan's Transformer Rebuilding,a set of five jobs is ready for dispatching to a machine center.The processing times and due dates for the jobs are given in the table below.Use shortest processing time to sequence the jobs,and calculate the average completion time,the average job lateness,and the average number of jobs in the machine center.


(Essay)
4.8/5
(36)
The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client.Accordingly,she has estimated the time it should take for each of her top consultants-Charlie,Gerald,Johnny,and Rick-to complete any of the four projects,as follows:
(a)What is the total number of hours required by the following arbitrary assignment?
Charlie→B;Gerald→A;Johnny→D;Rick→C
(b)What is the optimal assignment of consultants to projects? (Use the assignment method. )
(c)For the optimal schedule,what is the total number of hours it will take these consultants to complete these projects?

(Essay)
4.9/5
(38)
A manufacturer has the following jobs waiting on a single work center.The firm has not decided which dispatching rule to apply in order to prioritize the jobs and fix them into the schedule.Processing time in 15-minute time blocks and due date for each job are in the table below.
a.Complete the following table.Show your supporting calculations below.
b.Which dispatching rule has the best score for flow time? for work in process (jobs in the system)? for lateness?
c.Is there ANY sequence that can avoid all lateness? Explain or provide an example.



(Essay)
4.9/5
(39)
Delta uses mathematical short-term scheduling techniques and a high-tech nerve center to manage the rapid rescheduling necessary to cope with weather delays and similar disruptions.
(True/False)
4.8/5
(34)
Which of the following dispatching rules ordinarily gives the best results when the criterion is lowest time for completion of the full sequence of jobs?
(Multiple Choice)
4.8/5
(43)
Five jobs are waiting to be processed.Their processing times and due dates are given below.Using the earliest due date dispatching rule,in which order should the jobs be processed? 

(Multiple Choice)
4.9/5
(37)
What is the difference between a Gantt load chart and a Gantt scheduling chart?
(Essay)
4.8/5
(38)
The ________ is a special class of linear programming models that involves assigning tasks or jobs to resources.
(Essay)
4.9/5
(30)
Gantt charts are useful for scheduling jobs,but not for loading them.
(True/False)
4.8/5
(32)
The operations manager of a body and paint shop has five cars to schedule for repair.He would like to minimize the throughput time (makespan)to complete all work on these cars.Each car requires body work prior to painting.The estimates of the times required to do the body and paint work on each are as follows:
(a)Use Johnson's rule to sequence these five jobs for minimum total duration.Show your work in
determining the job sequence.
(b)The optimal sequence is ________.
(c)Chart the progress of the five jobs in this optimal sequence.
(d)After how many hours will all jobs be completed?

(Essay)
4.9/5
(37)
Compare short-term scheduling at process-focused,repetitive,and product-focused facilities.
(Essay)
4.9/5
(47)
Showing 21 - 40 of 116