Exam 8: Managing Projects
Exam 1: Creating Customer Value through Operations128 Questions
Exam 2: Supply Chain Management171 Questions
Exam 3: Process Configuration137 Questions
Exam 4: Capacity145 Questions
Exam 5: Inventory Management177 Questions
Exam 6: Quality and Process Improvement240 Questions
Exam 7: Lean Systems158 Questions
Exam 8: Managing Projects153 Questions
Exam 9: Location and Layout217 Questions
Exam 10: Managing Demand and Forecasting189 Questions
Exam 11: Operations Planning and Scheduling138 Questions
Exam 12: Resource Planning174 Questions
Exam 13: Decision Making82 Questions
Exam 14: Financial Analysis41 Questions
Exam 15: Work Measurement98 Questions
Exam 16: Learning Curve Analysis44 Questions
Exam 17: Computer-Integrated Manufacturing53 Questions
Exam 18: Acceptance Sampling Plans71 Questions
Exam 19: Simulation36 Questions
Exam 20: Special Inventory Models33 Questions
Exam 21: Linear Programming57 Questions
Exam 22: Waiting Lines109 Questions
Select questions type
Total slack for an activity is calculated by adding up the time required to complete all activities that follow the activity in the project.
(True/False)
4.8/5
(46)
________ simply adds more of an overloaded resource to maintain the schedule of an activity.
(Short Answer)
4.7/5
(45)
Activity slack refers to how much time an activity's completion time must be reduced by in order to shorten the critical path.
(True/False)
4.9/5
(37)
What options do project managers have to alleviate resource problems? Briefly describe each method.
(Essay)
4.8/5
(44)
Explain what the close out phase of the project life cycle involves.
(Essay)
4.8/5
(34)
The work breakdown structure is a statement of all work that has to be completed.
(True/False)
4.7/5
(38)
There are major differences between the program evaluation and review technique (PERT)and the critical path method (CPM)for network planning.
(True/False)
4.8/5
(35)
Table 3.10
You are responsible for managing a project with the following activities
(times are given in weeks).
Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 2 5 14 \@cdots B 8 11 14 \@cdots C 5 7 9 A D 6 9 12 A E 1 3 5 D,B
-Using Table 3.10,if the expected time for activity B is changed to 18 weeks,by how many weeks will the project's expected completion time increase?
(Multiple Choice)
4.8/5
(40)
Table 3.2
Time (days)
Activity Immediate Predecessor(s) Most Optimistic Most Likely Most Pessimistic A \@cdots 2 4 6 B \@cdots 1 4 7 C A 2 2 2 D B 1 7 10 E D 2 4 6 F E 1 2 3 G C 3 4 17 H D, G 3 7 11 I D 8 9 10 J F,H 4 5 6 K I 1 1 1
-Using Table 3.2,which activity is on the critical path?
(Multiple Choice)
4.8/5
(33)
A precedence relationship specifies that one activity cannot start until a preceding activity has been completed.
(True/False)
4.8/5
(40)
A precedence relationship specifies that one activity cannot start until a preceding activity has been started.
(True/False)
4.9/5
(36)
Showing 141 - 153 of 153
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)