Exam 8: Managing Projects
Exam 1: Creating Customer Value through Operations128 Questions
Exam 2: Supply Chain Management171 Questions
Exam 3: Process Configuration137 Questions
Exam 4: Capacity145 Questions
Exam 5: Inventory Management177 Questions
Exam 6: Quality and Process Improvement240 Questions
Exam 7: Lean Systems158 Questions
Exam 8: Managing Projects153 Questions
Exam 9: Location and Layout217 Questions
Exam 10: Managing Demand and Forecasting189 Questions
Exam 11: Operations Planning and Scheduling138 Questions
Exam 12: Resource Planning174 Questions
Exam 13: Decision Making82 Questions
Exam 14: Financial Analysis41 Questions
Exam 15: Work Measurement98 Questions
Exam 16: Learning Curve Analysis44 Questions
Exam 17: Computer-Integrated Manufacturing53 Questions
Exam 18: Acceptance Sampling Plans71 Questions
Exam 19: Simulation36 Questions
Exam 20: Special Inventory Models33 Questions
Exam 21: Linear Programming57 Questions
Exam 22: Waiting Lines109 Questions
Select questions type
Assume that activity G has the following times:
Early start time = 7 days
Early finish time = 13 days
Late start time = 15 days
Late finish time = 21 days
Which of the following statements is TRUE about activity G?
(Multiple Choice)
4.9/5
(34)
Table 3.4
Activity Immediate Predecessor(s) Time (weeks) A \@cdots 2 B \@cdots 2 C \@cdots 2 D A 2 E B 2 F B 2 G C 2 H E 2 I F 2 J D 2 K I 2 L K,H 2 M G 2 N L, J 2
-Using Table 3.4,the expected time to complete the whole project is
(Multiple Choice)
4.8/5
(37)
Table 3.8
Activity Immediate Predecessor(s) Time (weeks) A \@cdots 3 B \@cdots 4 C A,B 5 D A 6 E 4 F , 2
-Using Table 3.8,what is the earliest completion time of the project?
(Multiple Choice)
4.8/5
(31)
The ________ is the sequence of activities between a project's start and finish that takes the longest time to complete.
(Short Answer)
4.9/5
(31)
If a project has multiple critical paths,which of the following variances should be used in analyzing project completion time probabilities?
(Multiple Choice)
4.9/5
(42)
A hierarchical approach to developing a work breakdown structure (WBS)for a project involves breaking major work tasks down into smaller tasks.
(True/False)
4.9/5
(31)
In an activity-on-node (AON)network,the nodes represent ________ whereas the arcs represent ________.
(Multiple Choice)
4.8/5
(34)
Table 3.11
You are responsible for managing a project with the
following activities (times are given in days).
Activity Expected Time Immediate Predecessor(s) A 3 \@cdots B 6 -\@cdots C 2 \@cdots D 5 A E 2 C F 7 A G 4 B,D,E
-Using,Table 3.11,what is the critical path and expected completion time for this project?
(Multiple Choice)
4.9/5
(36)
Table 3.3
Activity Immediate Predecessor(s) Time (weeks) A \@cdots 3 B \@cdots 3 C \@cdots 3 D B 4 E A,C 4 F B 4 G H E 5 I E 5
-Using Table 3.3,what is the earliest completion time for this project?
(Multiple Choice)
4.8/5
(42)
The network diagram is a planning method that is designed to depict the relationships between activities.
(True/False)
4.8/5
(36)
In planning projects,the acronym WBS stands for "work behind schedule."
(True/False)
4.9/5
(39)
The additional cost associated with reducing an activity time is called ________.
(Short Answer)
4.9/5
(35)
The critical path is the sequence of activities between a project's start and finish that take the shortest time to complete.
(True/False)
4.9/5
(35)
Table 3.1
Time (weeks)
Activity Immediate Predecessor(s) Most Optimistic Most Likely Most Pessimistic A -1 1 2 3 B A 2 4 12 C A 1 2 3 D B 6 7 8 E B,C 10 12 14 F D 2 3 4 G E,F 1 5 15 H A 2 5 14
-Using Table 3.1,which activity will have the largest amount of slack?
(Multiple Choice)
5.0/5
(37)
Discuss the importance of establishing the scope,time frame,and resources to be allocated to a project before the project is actually started.
(Essay)
4.7/5
(32)
A Gantt chart is a project schedule that superimposes project activities on a time line.
(True/False)
4.8/5
(42)
Table 3.8
Activity Immediate Predecessor(s) Time (weeks) A \@cdots 3 B \@cdots 4 C A,B 5 D A 6 E 4 F , 2
-Using Table 3.8,what is the slack for activity A?
(Multiple Choice)
4.8/5
(40)
________ refers to a network planning method created for the U.S.Navy's Polaris missile project.
(Short Answer)
4.9/5
(35)
Standard computerized scheduling packages are rarely used for project management.