Exam 8: Managing Projects

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Scope creep is one of the primary causes of project failure.

(True/False)
4.9/5
(34)

Which one of the following statements about network diagrams is TRUE?

(Multiple Choice)
4.8/5
(35)

Which one of the following conditions violates the assumptions of PERT/CPM networks?

(Multiple Choice)
4.8/5
(36)

________ is the smallest unit of work effort consuming both time and resources that the project manager can schedule and control.

(Short Answer)
4.8/5
(37)

Assuming a beta distribution is being used,if the most optimistic time for an activity decreases by 12 days,what will happen to the expected time for that activity?

(Multiple Choice)
4.9/5
(36)

Among all the paths of activities in a project's network diagram,the critical path is the path with the most activity slack.

(True/False)
4.9/5
(36)

Table 3.3 Activity Immediate Predecessor(s) Time (weeks) A \@cdots 3 B \@cdots 3 C \@cdots 3 D B 4 E A,C 4 F B 4 G H E 5 I E 5 -Using Table 3.3,what is the minimum number of activities that would have to be crashed in order to cause a decrease in the project's earliest completion date?

(Multiple Choice)
4.8/5
(37)

________ is the shortest time in which an activity can be completed,if all goes exceptionally well.

(Short Answer)
4.8/5
(47)

One of duties of the project manager is to make sure that issues that have been raised during the project actually get resolved in a timely fashion.

(True/False)
4.7/5
(42)

A(n)________ determines the sequence for undertaking activities.

(Short Answer)
4.9/5
(41)

Scope creep refers to many small incremental changes to project objectives,which in total significantly expand the scope.

(True/False)
4.9/5
(41)

Describe what a work breakdown structure (WBS)is and briefly explain the approach followed to develop a WBS for a project.

(Essay)
4.7/5
(32)

Table 3.7 Activity Immediate Predecessor () Time (weeks) \@cdots 3 - \@cdots 4 2 , 4 ,, 2 , 1 6 , 2 ,, 4 , 3 6 -Using Table 3.7,suppose activity I is delayed,taking 8 weeks to complete instead of 2 weeks.Assume all other activity times remain the same.How much longer will the total project earliest completion time become?

(Multiple Choice)
5.0/5
(29)

Which of the following is NOT one of the five steps involved in planning projects?

(Multiple Choice)
4.8/5
(47)

Describe the four steps followed to determine the minimum-cost schedule for a project that is planned based on the critical path method (CPM).

(Essay)
4.8/5
(32)

The earliest start time (ES)for an activity is the maximum of the earliest finish (EF)times for all the activities that immediately precede the activity.

(True/False)
4.8/5
(33)

The ________ is the shortest time in which an activity can be completed if all goes exceptional well.

(Short Answer)
4.9/5
(40)

Crashing,or expediting,any activity within a project will reduce the overall project completion time.

(True/False)
4.9/5
(40)

Table 3.7 Activity Immediate Predecessor () Time (weeks) \@cdots 3 - \@cdots 4 2 , 4 ,, 2 , 1 6 , 2 ,, 4 , 3 6 -Using Table 3.7,what is the critical path for this project?

(Multiple Choice)
4.8/5
(36)

Table 3.11 You are responsible for managing a project with the following activities (times are given in days). Activity Expected Time Immediate Predecessor(s) A 3 \@cdots B 6 -\@cdots C 2 \@cdots D 5 A E 2 C F 7 A G 4 B,D,E -Using,Table 3.11,which of the following activities has the largest amount of slack?

(Multiple Choice)
4.9/5
(36)
Showing 101 - 120 of 153
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)