Exam 8: Managing Projects
Exam 1: Creating Customer Value through Operations128 Questions
Exam 2: Supply Chain Management171 Questions
Exam 3: Process Configuration137 Questions
Exam 4: Capacity145 Questions
Exam 5: Inventory Management177 Questions
Exam 6: Quality and Process Improvement240 Questions
Exam 7: Lean Systems158 Questions
Exam 8: Managing Projects153 Questions
Exam 9: Location and Layout217 Questions
Exam 10: Managing Demand and Forecasting189 Questions
Exam 11: Operations Planning and Scheduling138 Questions
Exam 12: Resource Planning174 Questions
Exam 13: Decision Making82 Questions
Exam 14: Financial Analysis41 Questions
Exam 15: Work Measurement98 Questions
Exam 16: Learning Curve Analysis44 Questions
Exam 17: Computer-Integrated Manufacturing53 Questions
Exam 18: Acceptance Sampling Plans71 Questions
Exam 19: Simulation36 Questions
Exam 20: Special Inventory Models33 Questions
Exam 21: Linear Programming57 Questions
Exam 22: Waiting Lines109 Questions
Select questions type
Which one of the following statements about network diagrams is TRUE?
(Multiple Choice)
4.8/5
(35)
Which one of the following conditions violates the assumptions of PERT/CPM networks?
(Multiple Choice)
4.8/5
(36)
________ is the smallest unit of work effort consuming both time and resources that the project manager can schedule and control.
(Short Answer)
4.8/5
(37)
Assuming a beta distribution is being used,if the most optimistic time for an activity decreases by 12 days,what will happen to the expected time for that activity?
(Multiple Choice)
4.9/5
(36)
Among all the paths of activities in a project's network diagram,the critical path is the path with the most activity slack.
(True/False)
4.9/5
(36)
Table 3.3
Activity Immediate Predecessor(s) Time (weeks) A \@cdots 3 B \@cdots 3 C \@cdots 3 D B 4 E A,C 4 F B 4 G H E 5 I E 5
-Using Table 3.3,what is the minimum number of activities that would have to be crashed in order to cause a decrease in the project's earliest completion date?
(Multiple Choice)
4.8/5
(37)
________ is the shortest time in which an activity can be completed,if all goes exceptionally well.
(Short Answer)
4.8/5
(47)
One of duties of the project manager is to make sure that issues that have been raised during the project actually get resolved in a timely fashion.
(True/False)
4.7/5
(42)
A(n)________ determines the sequence for undertaking activities.
(Short Answer)
4.9/5
(41)
Scope creep refers to many small incremental changes to project objectives,which in total significantly expand the scope.
(True/False)
4.9/5
(41)
Describe what a work breakdown structure (WBS)is and briefly explain the approach followed to develop a WBS for a project.
(Essay)
4.7/5
(32)
Table 3.7
Activity Immediate Predecessor () Time (weeks) \@cdots 3 - \@cdots 4 2 , 4 ,, 2 , 1 6 , 2 ,, 4 , 3 6
-Using Table 3.7,suppose activity I is delayed,taking 8 weeks to complete instead of 2 weeks.Assume all other activity times remain the same.How much longer will the total project earliest completion time become?
(Multiple Choice)
5.0/5
(29)
Which of the following is NOT one of the five steps involved in planning projects?
(Multiple Choice)
4.8/5
(47)
Describe the four steps followed to determine the minimum-cost schedule for a project that is planned based on the critical path method (CPM).
(Essay)
4.8/5
(32)
The earliest start time (ES)for an activity is the maximum of the earliest finish (EF)times for all the activities that immediately precede the activity.
(True/False)
4.8/5
(33)
The ________ is the shortest time in which an activity can be completed if all goes exceptional well.
(Short Answer)
4.9/5
(40)
Crashing,or expediting,any activity within a project will reduce the overall project completion time.
(True/False)
4.9/5
(40)
Table 3.7
Activity Immediate Predecessor () Time (weeks) \@cdots 3 - \@cdots 4 2 , 4 ,, 2 , 1 6 , 2 ,, 4 , 3 6
-Using Table 3.7,what is the critical path for this project?
(Multiple Choice)
4.8/5
(36)
Table 3.11
You are responsible for managing a project with the
following activities (times are given in days).
Activity Expected Time Immediate Predecessor(s) A 3 \@cdots B 6 -\@cdots C 2 \@cdots D 5 A E 2 C F 7 A G 4 B,D,E
-Using,Table 3.11,which of the following activities has the largest amount of slack?
(Multiple Choice)
4.9/5
(36)
Showing 101 - 120 of 153
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)