Many small incremental changes to project objectives,which in total significantly expand the scope are referred to as ________.

(Short Answer)
4.9/5
(41)

Resource allocation is an attempt to reduce the peaks and valleys in resource needs by shifting the schedules of conflicting activities within their earliest and latest start dates.

(True/False)
5.0/5
(32)

In a network diagram,an "activity"

(Multiple Choice)
4.9/5
(35)

Why do managers want to know the slack of activities?

(Essay)
4.9/5
(36)

The ________ cost refers to the additional cost associated with reducing an activity time in a project network.

(Short Answer)
4.9/5
(34)

Consider the tasks,durations,and predecessor relationships in the following network.Draw the network and answer the questions that follow. Activity Description Immediate Predecessor(s) Optimistic (Weeks) Most Likely (Weeks) Pessimistic (Weeks) A -\@cdots 4 7 10 B A 2 8 20 C A 8 12 16 D B 1 2 3 E D, C 6 8 22 F C 2 3 4 G F 2 2 2 H F 6 8 10 I E, G,H 4 8 12 J I 1 2 3 a.What is the expected time for activity B? b.What is the variance for activity B? c.Based on the calculation of estimated times,what is the critical path? d.What is the estimated time of the critical path? e.What is the activity variance along the critical path? f.What is the probability of completion of the project before week 42? You will need to refer to a standard normal table to answer the question.

(Essay)
4.9/5
(45)

Projects often cut across organizational lines.

(True/False)
4.8/5
(36)

If one activity along the critical path is delayed,the entire project will be delayed.

(True/False)
4.8/5
(33)

A(n)________ chart is a project schedule that superimposes project activities,with their precedence relationships and estimated duration times,on a time line.

(Short Answer)
4.8/5
(35)

Before beginning to create a PERT/CPM network model for a project,the project must be described in general terms.Two types of information that must be defined are

(Multiple Choice)
4.8/5
(44)

Typically activities along the critical path have more slack than activities not on the critical path.

(True/False)
4.8/5
(40)

Each activity in the work breakdown structure must have an "owner" who is responsible for doing the work.

(True/False)
4.8/5
(26)

The ________ is the longest estimated time required to perform an activity.

(Short Answer)
4.9/5
(35)

The duration of an entire project is determined by the earliest finish time (EF)for the last activity on the critical path.

(True/False)
4.7/5
(38)

Table 3.1 Time (weeks) Activity Immediate Predecessor(s) Most Optimistic Most Likely Most Pessimistic A -1 1 2 3 B A 2 4 12 C A 1 2 3 D B 6 7 8 E B,C 10 12 14 F D 2 3 4 G E,F 1 5 15 H A 2 5 14 -Using Table 3.1,if the expected times for activities A,G,and H increased by 2,3,and 4 weeks,respectively,by how many weeks would the project's earliest expected time of completion increase?

(Multiple Choice)
4.8/5
(37)

Table 3.5 Activity Immediate Predecessor(s) Time (weeks) A \@cdots 6 B \@cdots 3 C A,B 2 D A 6 E C 2 F D,E 2 G C 8 -Using Table 3.5,what is the earliest completion time of this project?

(Multiple Choice)
4.8/5
(42)

Table 3.7 Activity Immediate Predecessor () Time (weeks) \@cdots 3 - \@cdots 4 2 , 4 ,, 2 , 1 6 , 2 ,, 4 , 3 6 -Using Table 3.7,suppose activity D can be shortened from 4 weeks to 1 week.Assume all other activity times remain the same.How much shorter will the total project earliest completion time become?

(Multiple Choice)
4.8/5
(36)

Table 3.7 Activity Immediate Predecessor () Time (weeks) \@cdots 3 - \@cdots 4 2 , 4 ,, 2 , 1 6 , 2 ,, 4 , 3 6 -Using Table 3.7,what is the latest start time for activity A?

(Multiple Choice)
4.9/5
(38)

The probability that a project will be completed by its earliest expected completion date is

(Multiple Choice)
4.9/5
(46)

Table 3.3 Activity Immediate Predecessor(s) Time (weeks) A \@cdots 3 B \@cdots 3 C \@cdots 3 D B 4 E A,C 4 F B 4 G H E 5 I E 5 -Using Table 3.3,what is the largest amount of slack that any activity in the project has?

(Multiple Choice)
4.7/5
(44)