When using the beta distribution for estimating activity times,

(Multiple Choice)
4.9/5
(38)

What are the benefits of using CPM/PERT?

(Essay)
4.7/5
(30)

Table 3.12 You are responsible for managing a project with the following activities (times are given in weeks). Activity Expected Time Immediate Predecessor () 3 \@cdots- B 3 - C 5 A D 4 A,B E 4 B F 4 C,D G 3 , 5 , -Using Table 3.12,which of the following activities has the largest amount of slack?

(Multiple Choice)
4.9/5
(41)

To calculate the probability of completing a project by a certain date,

(Multiple Choice)
5.0/5
(34)

What characteristics should project manager possess?

(Essay)
4.8/5
(37)

Table 3.10 You are responsible for managing a project with the following activities (times are given in weeks). Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 2 5 14 \@cdots B 8 11 14 \@cdots C 5 7 9 A D 6 9 12 A E 1 3 5 D,B -Using Table 3.10,what is the probability that the project will take 16 or more weeks to complete? You will need to refer to a standard normal table to answer the question.

(Multiple Choice)
4.8/5
(42)

Which one of the following best describes the critical path of a PERT/CPM network?

(Multiple Choice)
4.8/5
(44)

Risk is a measure of the probability and consequences of not reaching a defined project goal.

(True/False)
4.9/5
(43)

Projects cannot have more than one critical path.

(True/False)
4.9/5
(32)

Table 3.3 Activity Immediate Predecessor(s) Time (weeks) A \@cdots 3 B \@cdots 3 C \@cdots 3 D B 4 E A,C 4 F B 4 G H E 5 I E 5 -Using Table 3.3,what is the minimum number of activities that would have to be delayed in order to cause an increase in the project's earliest completion date?

(Multiple Choice)
5.0/5
(30)

The optimistic time is the probable time required to perform the activity.

(True/False)
4.8/5
(40)

Table 3.5 Activity Immediate Predecessor(s) Time (weeks) A \@cdots 6 B \@cdots 3 C A,B 2 D A 6 E C 2 F D,E 2 G C 8 -Using Table 3.5,what is the critical path of this project?

(Multiple Choice)
4.8/5
(32)

Table 3.4 Activity Immediate Predecessor(s) Time (weeks) A \@cdots 2 B \@cdots 2 C \@cdots 2 D A 2 E B 2 F B 2 G C 2 H E 2 I F 2 J D 2 K I 2 L K,H 2 M G 2 N L, J 2 -Using Table 3.4,of the following activities,which one has a slack value greater than zero weeks?

(Multiple Choice)
4.9/5
(32)

Table 3.10 You are responsible for managing a project with the following activities (times are given in weeks). Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 2 5 14 \@cdots B 8 11 14 \@cdots C 5 7 9 A D 6 9 12 A E 1 3 5 D,B -Using Table 3.10,what is the probability of completing the project in 17 weeks or less? You will need to refer to a standard normal table to answer the question.

(Multiple Choice)
4.8/5
(34)

Table 3.4 Activity Immediate Predecessor(s) Time (weeks) A \@cdots 2 B \@cdots 2 C \@cdots 2 D A 2 E B 2 F B 2 G C 2 H E 2 I F 2 J D 2 K I 2 L K,H 2 M G 2 N L, J 2 -Using Table 3.4,what is the latest finish time for activity D?

(Multiple Choice)
4.9/5
(34)

Table 3.2 Time (days) Activity Immediate Predecessor(s) Most Optimistic Most Likely Most Pessimistic A \@cdots 2 4 6 B \@cdots 1 4 7 C A 2 2 2 D B 1 7 10 E D 2 4 6 F E 1 2 3 G C 3 4 17 H D, G 3 7 11 I D 8 9 10 J F,H 4 5 6 K I 1 1 1 -Using Table 3.2,if the project manager wants at least a 98% probability that the project will be completed on or before the due date,what is the shortest project due date that will satisfy the manager? You will need to refer to a standard normal table to answer the question.

(Multiple Choice)
4.8/5
(31)

The activities along the critical path determine the completion time for the project.

(True/False)
4.9/5
(41)

Table 3.12 You are responsible for managing a project with the following activities (times are given in weeks). Activity Expected Time Immediate Predecessor () 3 \@cdots- B 3 - C 5 A D 4 A,B E 4 B F 4 C,D G 3 , 5 , -Using Table 3.12,what is the critical path for this network?

(Multiple Choice)
4.9/5
(35)

Free slack is the amount of time that an activity's earliest finish time can be delayed without delaying the earliest start time of any activity immediately following it.

(True/False)
4.8/5
(39)

A critical path is the sequence of activities between a project's start and finish.

(True/False)
4.9/5
(35)