Exam 8: Managing Projects
Exam 1: Creating Customer Value through Operations128 Questions
Exam 2: Supply Chain Management171 Questions
Exam 3: Process Configuration137 Questions
Exam 4: Capacity145 Questions
Exam 5: Inventory Management177 Questions
Exam 6: Quality and Process Improvement240 Questions
Exam 7: Lean Systems158 Questions
Exam 8: Managing Projects153 Questions
Exam 9: Location and Layout217 Questions
Exam 10: Managing Demand and Forecasting189 Questions
Exam 11: Operations Planning and Scheduling138 Questions
Exam 12: Resource Planning174 Questions
Exam 13: Decision Making82 Questions
Exam 14: Financial Analysis41 Questions
Exam 15: Work Measurement98 Questions
Exam 16: Learning Curve Analysis44 Questions
Exam 17: Computer-Integrated Manufacturing53 Questions
Exam 18: Acceptance Sampling Plans71 Questions
Exam 19: Simulation36 Questions
Exam 20: Special Inventory Models33 Questions
Exam 21: Linear Programming57 Questions
Exam 22: Waiting Lines109 Questions
Select questions type
When using the beta distribution for estimating activity times,
(Multiple Choice)
4.9/5
(38)
Table 3.12
You are responsible for managing a project with the following activities (times are given in weeks).
Activity Expected Time Immediate Predecessor () 3 \@cdots- B 3 - C 5 A D 4 A,B E 4 B F 4 C,D G 3 , 5 ,
-Using Table 3.12,which of the following activities has the largest amount of slack?
(Multiple Choice)
4.9/5
(41)
To calculate the probability of completing a project by a certain date,
(Multiple Choice)
5.0/5
(34)
Table 3.10
You are responsible for managing a project with the following activities
(times are given in weeks).
Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 2 5 14 \@cdots B 8 11 14 \@cdots C 5 7 9 A D 6 9 12 A E 1 3 5 D,B
-Using Table 3.10,what is the probability that the project will take 16 or more weeks to complete? You will need to refer to a standard normal table to answer the question.
(Multiple Choice)
4.8/5
(42)
Which one of the following best describes the critical path of a PERT/CPM network?
(Multiple Choice)
4.8/5
(44)
Risk is a measure of the probability and consequences of not reaching a defined project goal.
(True/False)
4.9/5
(43)
Table 3.3
Activity Immediate Predecessor(s) Time (weeks) A \@cdots 3 B \@cdots 3 C \@cdots 3 D B 4 E A,C 4 F B 4 G H E 5 I E 5
-Using Table 3.3,what is the minimum number of activities that would have to be delayed in order to cause an increase in the project's earliest completion date?
(Multiple Choice)
5.0/5
(30)
The optimistic time is the probable time required to perform the activity.
(True/False)
4.8/5
(40)
Table 3.5
Activity Immediate Predecessor(s) Time (weeks) A \@cdots 6 B \@cdots 3 C A,B 2 D A 6 E C 2 F D,E 2 G C 8
-Using Table 3.5,what is the critical path of this project?
(Multiple Choice)
4.8/5
(32)
Table 3.4
Activity Immediate Predecessor(s) Time (weeks) A \@cdots 2 B \@cdots 2 C \@cdots 2 D A 2 E B 2 F B 2 G C 2 H E 2 I F 2 J D 2 K I 2 L K,H 2 M G 2 N L, J 2
-Using Table 3.4,of the following activities,which one has a slack value greater than zero weeks?
(Multiple Choice)
4.9/5
(32)
Table 3.10
You are responsible for managing a project with the following activities
(times are given in weeks).
Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 2 5 14 \@cdots B 8 11 14 \@cdots C 5 7 9 A D 6 9 12 A E 1 3 5 D,B
-Using Table 3.10,what is the probability of completing the project in 17 weeks or less? You will need to refer to a standard normal table to answer the question.
(Multiple Choice)
4.8/5
(34)
Table 3.4
Activity Immediate Predecessor(s) Time (weeks) A \@cdots 2 B \@cdots 2 C \@cdots 2 D A 2 E B 2 F B 2 G C 2 H E 2 I F 2 J D 2 K I 2 L K,H 2 M G 2 N L, J 2
-Using Table 3.4,what is the latest finish time for activity D?
(Multiple Choice)
4.9/5
(34)
Table 3.2
Time (days)
Activity Immediate Predecessor(s) Most Optimistic Most Likely Most Pessimistic A \@cdots 2 4 6 B \@cdots 1 4 7 C A 2 2 2 D B 1 7 10 E D 2 4 6 F E 1 2 3 G C 3 4 17 H D, G 3 7 11 I D 8 9 10 J F,H 4 5 6 K I 1 1 1
-Using Table 3.2,if the project manager wants at least a 98% probability that the project will be completed on or before the due date,what is the shortest project due date that will satisfy the manager? You will need to refer to a standard normal table to answer the question.
(Multiple Choice)
4.8/5
(31)
The activities along the critical path determine the completion time for the project.
(True/False)
4.9/5
(41)
Table 3.12
You are responsible for managing a project with the following activities (times are given in weeks).
Activity Expected Time Immediate Predecessor () 3 \@cdots- B 3 - C 5 A D 4 A,B E 4 B F 4 C,D G 3 , 5 ,
-Using Table 3.12,what is the critical path for this network?
(Multiple Choice)
4.9/5
(35)
Free slack is the amount of time that an activity's earliest finish time can be delayed without delaying the earliest start time of any activity immediately following it.
(True/False)
4.8/5
(39)
A critical path is the sequence of activities between a project's start and finish.
(True/False)
4.9/5
(35)