Statement: In PERT, the mean (expected) time for each activity is determined by using a formula that gives the greatest weight to the "optimistic" time estimate.

(True/False)
4.8/5
(29)

Contingencies should be built in at the following level:

(Multiple Choice)
4.9/5
(39)

If the project completion has a distribution with Te = 15 weeks and Vp = 9, what is the probability that the project will be completed in less than 18 weeks? To answer this, the correct z value is:

(Multiple Choice)
4.8/5
(41)

A project cannot have more than one ___________buffer.

(Multiple Choice)
4.9/5
(38)

The Following Questions adapted from tutorial material of H Steyn Ed., Project Management -A Multi-disciplinary Approach (Pretoria: FPM Publishing, 2003). Reprinted with permission. -Put checks in the appropriate boxes in the table below. Project buffer Feeding buffer Resource buffer Drum buffer This buffer/ these buffers ensure(s) that, unlike the critical path, the critical chain does not change from time to time during project execution. This buffer/ these buffers ensure(s) that jobs done faster than planned contribute to reduced project duration. Action is required when this/these buffer(s) is/are say 67\% depleted. This/these buffer(s) contain a contingency reserve that has been removed from activities. If activities are done faster than planned, it could cause that this/these buffer(s) could get depleted (i.e. get smaller). This/these buffer(s) is/are never used on a single project.

(Short Answer)
4.8/5
(33)

When there are multiple critical paths and the project duration must be reduced, it is necessary to make reductions:

(Multiple Choice)
5.0/5
(30)

Which statement is incorrect:

(Multiple Choice)
5.0/5
(36)

The following buffer enables the project manager to focus on critical activities by ensuring that the critical chain does not change during project execution:

(Multiple Choice)
4.8/5
(26)

Statement: In resource loading, the project schedule is altered in an attempt to increase variations in the amount of the resource needed throughout the project.

(True/False)
4.9/5
(51)