Exam 8: Advanced Project Network Analysis and Scheduling
Exam 1: What Is Project Management12 Questions
Exam 2: Systems Approach28 Questions
Exam 3: Project Life Cycle and Project Conception32 Questions
Exam 4: Project Definition and System Definition42 Questions
Exam 5: Project Execution and Closeout32 Questions
Exam 6: Basic Project Planning Techniques32 Questions
Exam 7: Project Schedule Planning and Networks26 Questions
Exam 8: Advanced Project Network Analysis and Scheduling29 Questions
Exam 9: Cost Estimating and Budgeting29 Questions
Exam 10: Project Quality Management11 Questions
Exam 11: Project Risk Management31 Questions
Exam 12: Project Procurement Management and Contracting36 Questions
Exam 13: Project Monitoring and Control41 Questions
Exam 14: Agile Project Management and Lean27 Questions
Exam 15: Project Organizational Structure and Integration22 Questions
Exam 16: Project Roles and Stakeholders22 Questions
Exam 17: Leadership, Teamwork, and Conflict30 Questions
Exam 18: Meta-Management of Projects and Program Management38 Questions
Exam 19: Project Selection and Portfolio Management40 Questions
Exam 20: International Project Management45 Questions
Select questions type
Statement: In PERT, the mean (expected) time for each activity is determined by using a formula that gives the greatest weight to the "optimistic" time estimate.
(True/False)
4.8/5
(29)
If the project completion has a distribution with Te = 15 weeks and Vp = 9, what is the probability that the project will be completed in less than 18 weeks? To answer this, the correct z value is:
(Multiple Choice)
4.8/5
(41)
The Following Questions adapted from tutorial material of H Steyn Ed., Project Management -A Multi-disciplinary Approach (Pretoria: FPM Publishing, 2003). Reprinted with permission.
-Put checks in the appropriate boxes in the table below.
Project buffer Feeding buffer Resource buffer Drum buffer This buffer/ these buffers ensure(s) that, unlike the critical path, the critical chain does not change from time to time during project execution. This buffer/ these buffers ensure(s) that jobs done faster than planned contribute to reduced project duration. Action is required when this/these buffer(s) is/are say 67\% depleted. This/these buffer(s) contain a contingency reserve that has been removed from activities. If activities are done faster than planned, it could cause that this/these buffer(s) could get depleted (i.e. get smaller). This/these buffer(s) is/are never used on a single project.
(Short Answer)
4.8/5
(33)
When there are multiple critical paths and the project duration must be reduced, it is necessary to make reductions:
(Multiple Choice)
5.0/5
(30)
The following buffer enables the project manager to focus on critical activities by ensuring that the critical chain does not change during project execution:
(Multiple Choice)
4.8/5
(26)
Statement: In resource loading, the project schedule is altered in an attempt to increase variations in the amount of the resource needed throughout the project.
(True/False)
4.9/5
(51)