Exam 7: A: Design of Work Systems
Exam 1: Introduction to Operations Management63 Questions
Exam 2: Competitiveness, Strategic Planning, and Productivity54 Questions
Exam 3: Demand Forecasting172 Questions
Exam 4: A: Product Design74 Questions
Exam 4: B: Product Design56 Questions
Exam 5: A: Strategic Capacity Planning74 Questions
Exam 5: B: Strategic Capacity Planning64 Questions
Exam 6: A: Process Design and Facility Layout157 Questions
Exam 6: B: Process Design and Facility Layout99 Questions
Exam 7: A: Design of Work Systems143 Questions
Exam 7: B: Design of Work Systems68 Questions
Exam 8: A: Location Planning and Analysis74 Questions
Exam 8: B: Location Planning and Analysis16 Questions
Exam 9: Management of Quality98 Questions
Exam 10: A: Statistical Quality Control121 Questions
Exam 10: B: Statistical Quality Control61 Questions
Exam 11: Supply Chain Management86 Questions
Exam 12: Inventory Management168 Questions
Exam 13: Aggregate Operations Planning71 Questions
Exam 14: Material Requirements Planning and Enterprise Resource Planning84 Questions
Exam 15: A: Just-In-Time and Lean Production82 Questions
Exam 15: B: Just-In-Time and Lean Production32 Questions
Exam 16: Job and Staff Scheduling112 Questions
Exam 17: Project Management127 Questions
Exam 18: A: Waiting-Line Analysis76 Questions
Exam 18: B: Waiting-Line Analysis41 Questions
Select questions type
A performance rating of greater than 1.00 means that the observed worker was judged to be working faster than the normal rate.
(True/False)
4.7/5
(38)
A job has a normal time of 12 minutes,a performance rating of 0.80,and an allowance proportion of 20 percent of the workday.The standard time for this job in minutes is:
(Multiple Choice)
4.7/5
(38)
Which of the following is not one of the techniques used in motion study analysis?
(Multiple Choice)
4.8/5
(34)
-How many observations would be needed to be 95.44% confident that the maximum error in the observed time is 1 second?
Assume that the standard deviation of the task time is 2 seconds.

(Short Answer)
4.8/5
(33)
A time study of a job produced the following:
average cycle time = 1.5 minutes,performance rating = 1.15.Allowances are 18 percent of the work day (480 minutes).Determine the standard time for this job.
(Essay)
4.9/5
(39)
The name Frederick Winslow Taylor is associated with the scientific management approach to work/job design.
(True/False)
4.9/5
(38)
-If the person observed worked at a pace that is 20 percent faster than average,what should be the normal time for this task?

(Short Answer)
4.9/5
(44)
How many observations should be made if she wants to be 0.8664 confident that the maximum error in the observed time is 0.5 second? Assume that the standard deviation of the task time is 4 seconds.
(Multiple Choice)
4.8/5
(41)
Which of the following is not an accurate statement concerning the use of predetermined time standards for work measurement?
(Multiple Choice)
4.7/5
(41)
A work sampling study of dockworkers must be set up.There will be a large number of random observations.However,for this exercise,determine an observation schedule (arranged chronologically)for six observations.Assume workers are on the docks for eight hours a day,and that the study will be done over a 60-day period.Use the random digits listed below.


(Essay)
4.8/5
(41)
"Gain sharing" and "profit sharing" are equivalent types of bonus/incentive plans that focus exclusively on individual output.
(True/False)
4.9/5
(37)
Specialization is a primary point of disagreement between the efficiency and behavioural approaches to job design.
(True/False)
4.7/5
(40)
The Canadian Labour Code focuses on laws concerning wages and the right to form unions,not the safety and welfare of workers.
(True/False)
4.7/5
(38)
The behavioural approach to job design which involves giving the worker a larger portion of the total task is:
(Multiple Choice)
4.8/5
(32)
The technique which can be used to estimate the percentage of time a worker or a piece of equipment is idle is:
(Multiple Choice)
4.9/5
(35)
Methods analysis techniques do not directly consider behavioural aspects of jobs.
(True/False)
4.9/5
(37)
The methods analysis chart which describes the overall sequence of operations,including storages,delays,and inspections is a(n):
(Multiple Choice)
4.8/5
(31)
What is the standard time (ST)for this task if the employee worked at a twenty-five percent faster pace than the average and an allowance of twenty percent of the workday is used?