Exam 13: Progress and Performance Measurement and Evaluation
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection88 Questions
Exam 3: Organization: Structure and Culture94 Questions
Exam 4: Defining the Project89 Questions
Exam 5: Estimating Project Times and Costs91 Questions
Exam 6: Developing a Project Plan94 Questions
Exam 7: Managing Risk87 Questions
Exam 8: Scheduling Resources and Costs90 Questions
Exam 9: Reducing Project Duration94 Questions
Exam 10: Leadership: Being an Effective Project Manager88 Questions
Exam 11: Managing Project Teams94 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations94 Questions
Exam 13: Progress and Performance Measurement and Evaluation88 Questions
Exam 14: Project Closure88 Questions
Exam 15: International Projects94 Questions
Exam 16: Oversight86 Questions
Exam 17: An Introduction to Agile Project Management85 Questions
Exam 18: Project Management Career Paths35 Questions
Select questions type
Interpret the results of calculating the performance indexes based on a range of possible calculated values.
(Essay)
4.8/5
(39)
A typical project progress report would contain all of the following sections except:
(Multiple Choice)
4.8/5
(41)
The rule of using subjective estimated percent complete in combination with hard, tangible monitoring points works well on long-duration activities that can be broken into short discrete work packages.
(True/False)
4.8/5
(35)
Earned value is calculated by taking the percent complete times the original budget.
(True/False)
4.8/5
(36)
The ________ indexes compare the to-date progress to the end of the project.
(Short Answer)
4.9/5
(30)
The percent complete index that looks at percent complete in terms of budgeted amounts is calculated by which of the following?
(Multiple Choice)
4.8/5
(38)
All scope changes that result in increased costs should be avoided.
(True/False)
4.9/5
(38)
The ________ is the difference between the earned value and the actual costs for the work completed to date.
(Short Answer)
4.9/5
(36)
A tool used to monitor past project schedule performance, current performance, and to estimate future schedule trends is a simple line chart known as a:
(Multiple Choice)
4.8/5
(29)
What is the difference between a baseline Gantt chart and a Tracking Gantt chart?
(Essay)
4.9/5
(32)
An undesirable schedule variance indicates that the project is running behind schedule.
(True/False)
4.8/5
(46)
Which of the following are required to assess the current status of a project using the earned-value cost/schedule system?
(Multiple Choice)
4.9/5
(33)
The percent complete index that looks at percent complete in terms of actual amounts is calculated by which of the following?
(Multiple Choice)
5.0/5
(31)
In a project control chart, four observations trending in one direction indicate there is a very high probability that there is an identifiable cause.
(True/False)
4.8/5
(36)
Measuring performance against budget is simply a case of comparing actual versus budget.
(True/False)
4.8/5
(35)
The network chart is the most favored, used, and understandable option for reporting project progress to upper management.
(True/False)
4.7/5
(37)
Earned value is defined as the budgeted cost of the work performed.
(True/False)
4.8/5
(38)
Showing 41 - 60 of 88
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)