Exam 13: Progress and Performance Measurement and Evaluation

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Interpret the results of calculating the performance indexes based on a range of possible calculated values.

(Essay)
4.8/5
(39)

A typical project progress report would contain all of the following sections except:

(Multiple Choice)
4.8/5
(41)

The rule of using subjective estimated percent complete in combination with hard, tangible monitoring points works well on long-duration activities that can be broken into short discrete work packages.

(True/False)
4.8/5
(35)

Earned value is calculated by taking the percent complete times the original budget.

(True/False)
4.8/5
(36)

The ________ indexes compare the to-date progress to the end of the project.

(Short Answer)
4.9/5
(30)

CPI and SPI are two types of indexes that measure ________.

(Short Answer)
4.8/5
(38)

The percent complete index that looks at percent complete in terms of budgeted amounts is calculated by which of the following?

(Multiple Choice)
4.8/5
(38)

All scope changes that result in increased costs should be avoided.

(True/False)
4.9/5
(38)

The ________ is the difference between the earned value and the actual costs for the work completed to date.

(Short Answer)
4.9/5
(36)

A tool used to monitor past project schedule performance, current performance, and to estimate future schedule trends is a simple line chart known as a:

(Multiple Choice)
4.8/5
(29)

A typical tool used to communicate project status is a:

(Multiple Choice)
4.8/5
(34)

What is the difference between a baseline Gantt chart and a Tracking Gantt chart?

(Essay)
4.9/5
(32)

An undesirable schedule variance indicates that the project is running behind schedule.

(True/False)
4.8/5
(46)

Which of the following are required to assess the current status of a project using the earned-value cost/schedule system?

(Multiple Choice)
4.9/5
(33)

Baseline project budgets are derived from:

(Multiple Choice)
4.8/5
(28)

The percent complete index that looks at percent complete in terms of actual amounts is calculated by which of the following?

(Multiple Choice)
5.0/5
(31)

In a project control chart, four observations trending in one direction indicate there is a very high probability that there is an identifiable cause.

(True/False)
4.8/5
(36)

Measuring performance against budget is simply a case of comparing actual versus budget.

(True/False)
4.8/5
(35)

The network chart is the most favored, used, and understandable option for reporting project progress to upper management.

(True/False)
4.7/5
(37)

Earned value is defined as the budgeted cost of the work performed.

(True/False)
4.8/5
(38)
Showing 41 - 60 of 88
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)