Exam 13: Progress and Performance Measurement and Evaluation
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection88 Questions
Exam 3: Organization: Structure and Culture94 Questions
Exam 4: Defining the Project89 Questions
Exam 5: Estimating Project Times and Costs91 Questions
Exam 6: Developing a Project Plan94 Questions
Exam 7: Managing Risk87 Questions
Exam 8: Scheduling Resources and Costs90 Questions
Exam 9: Reducing Project Duration94 Questions
Exam 10: Leadership: Being an Effective Project Manager88 Questions
Exam 11: Managing Project Teams94 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations94 Questions
Exam 13: Progress and Performance Measurement and Evaluation88 Questions
Exam 14: Project Closure88 Questions
Exam 15: International Projects94 Questions
Exam 16: Oversight86 Questions
Exam 17: An Introduction to Agile Project Management85 Questions
Exam 18: Project Management Career Paths35 Questions
Select questions type
The first step in the project control process of the measurement and evaluation of project performance is to
(Multiple Choice)
4.9/5
(40)
Typically, project progress reports are designed and communicated in written or oral form.Identify the common topic format for such progress reports.
(Essay)
4.8/5
(36)
Control charts are frequently used to monitor progress toward ________, which mark events and as such have zero duration.
(Short Answer)
4.8/5
(39)
Identify the four indexes used in project management control and identify the formulas for calculating the indexes.
(Essay)
4.8/5
(36)
A CPI index of 0.97 indicates that the project has spent less money than budgeted.
(True/False)
4.7/5
(38)
Generally the method for measuring accomplishments centers on comparing
(Multiple Choice)
4.7/5
(31)
Which of the following will calculate the To Complete Performance Index?
(Multiple Choice)
4.8/5
(26)
Overhead costs and profit are typically included in the project baseline.
(True/False)
4.8/5
(31)
What is scope creep and why should a project manager be concerned about it?
(Essay)
5.0/5
(37)
________ holds people accountable, prevents small problems from mushrooming into large problems, and keeps focus.
(Short Answer)
4.8/5
(30)
A positive variance in SV or CV indicates a ________ condition.
(Short Answer)
4.9/5
(33)
Because of their easy-to-understand visual format, ________ are the most favored, used, and understandable tool used to report project status.
(Short Answer)
4.8/5
(33)
Baseline costs typically include labor, equipment, materials and direct overhead cost.
(True/False)
4.8/5
(30)
The best method for assigning costs to the baseline under this rule is to establish frequent checkpoints over the duration of the work package and assign completion percentages in dollar terms.
(True/False)
4.9/5
(31)
In calculating schedule variance and cost variance, a negative variance indicates a desirable condition, and a positive variance suggests problems.
(True/False)
4.8/5
(35)