Exam 9: Reducing Project Duration

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Subtracting an activity's normal cost from the crash cost will calculate an activity's ________.

(Short Answer)
4.8/5
(37)

Because direct costs are assumed to be developed from normal methods and time, any reduction in activity time should add to the costs of the activity.

(True/False)
4.9/5
(34)

Project costs are generally classified as ____ costs.

(Multiple Choice)
4.7/5
(34)

Direct costs are assignable directly to a project ________.

(Short Answer)
4.8/5
(29)

When considering whether to move the project to its optimum cost-time position, the manager should also consider ________.

(Short Answer)
4.8/5
(43)

Creating a Project Cost-Duration Graph in the pre-project planning phase without an imposed duration is the best time to use this tool.

(True/False)
4.8/5
(41)

____________ is the rearranging of the project network logic so that critical activities are done in parallel rather than sequentially.

(Short Answer)
4.8/5
(32)

Because direct costs are assumed to be developed from normal methods and time, any reduction in activity time should ________ the cost of the activity.

(Short Answer)
4.7/5
(40)

In selecting the best activity to reduce you would first select the activity with the

(Multiple Choice)
4.8/5
(38)

What do we mean when we say that a project network is sensitive and why is that important to a project manager?

(Essay)
4.7/5
(49)

Intense global competition and rapid technological advances combine to create a(n) ________ imposed project duration date.

(Short Answer)
4.8/5
(34)

A rule of thumb for moderate- to high-technology firms is that a six-month delay in bringing a product to market can result in a gross profit loss of about 35 percent.

(True/False)
4.8/5
(41)

Identify and give an example for both of the major categories that make up project costs.

(Essay)
4.8/5
(35)

While the relationship between normal and crash times is really curvilinear, the assumption that it is linear is seldom a concern for practicing managers.

(True/False)
4.8/5
(51)
Showing 81 - 94 of 94
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)