Exam 9: Reducing Project Duration

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Indirect costs generally represent overhead costs such as supervision, administration, consultants, and interest.

(True/False)
4.9/5
(28)

A contractor finished a bridge across a lake 18 months early and received more than $6 million for the early completion.This is an example of reducing project duration caused by:

(Multiple Choice)
4.8/5
(33)

Low-cost, realistic, efficient methods for completing an activity under normal conditions are supported by ____ time.

(Multiple Choice)
4.9/5
(34)

According to Brooks' Law, adding more people to a late project is most likely to have which of the following impact?

(Multiple Choice)
4.8/5
(39)

Direct costs are so named because they can be assigned directly to a work package and activity.

(True/False)
4.9/5
(37)

Given that an activity's normal time and cost are ten days and $400, and its crash time is five days and $800, what is the activity's slope?

(Essay)
4.8/5
(45)

To shorten the duration of a project the project manager should limit the choices of activities to just those which ________.

(Short Answer)
4.9/5
(47)

A project network is classified as sensitive if it has a large number of interacting paths.

(True/False)
4.8/5
(34)

Costs such as supervision, administration, consultants, and interest are examples of ________ project costs.

(Short Answer)
4.8/5
(30)

Intense global competition and rapid technological advances create pressure on developing projects rapidly.This is an example of reducing project duration caused by:

(Multiple Choice)
4.8/5
(38)

Which of the following is the easiest method for shortening project time?

(Multiple Choice)
4.7/5
(42)

Which of the following correctly calculates an activity's cost slope?

(Multiple Choice)
4.8/5
(32)

A positive situation where moving toward the optimum time can result in very real, large savings-this occurs when the network is:

(Multiple Choice)
4.9/5
(32)

Imposed project durations almost always leads to a higher-cost project than one planned with detailed scheduling of all the project's activities.

(True/False)
4.9/5
(38)

If a network has several critical or near-critical paths it is deemed to be:

(Multiple Choice)
4.8/5
(36)

An activity's crash costs include ____ costs.

(Multiple Choice)
5.0/5
(37)

Crashing a more expensive activity may be wise if fewer inherent risks are involved.

(True/False)
4.9/5
(35)

The less steep the cost slope of an activity, the

(Multiple Choice)
4.8/5
(40)

An activity's cost slope represents an activity's

(Multiple Choice)
4.8/5
(31)

Which of the following is not one of the more commonly used options for cutting project costs?

(Multiple Choice)
4.8/5
(35)
Showing 21 - 40 of 94
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)