Exam 9: Reducing Project Duration
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection88 Questions
Exam 3: Organization: Structure and Culture94 Questions
Exam 4: Defining the Project89 Questions
Exam 5: Estimating Project Times and Costs91 Questions
Exam 6: Developing a Project Plan94 Questions
Exam 7: Managing Risk87 Questions
Exam 8: Scheduling Resources and Costs90 Questions
Exam 9: Reducing Project Duration94 Questions
Exam 10: Leadership: Being an Effective Project Manager88 Questions
Exam 11: Managing Project Teams94 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations94 Questions
Exam 13: Progress and Performance Measurement and Evaluation88 Questions
Exam 14: Project Closure88 Questions
Exam 15: International Projects94 Questions
Exam 16: Oversight86 Questions
Exam 17: An Introduction to Agile Project Management85 Questions
Exam 18: Project Management Career Paths35 Questions
Select questions type
Indirect costs generally represent overhead costs such as supervision, administration, consultants, and interest.
(True/False)
4.9/5
(28)
A contractor finished a bridge across a lake 18 months early and received more than $6 million for the early completion.This is an example of reducing project duration caused by:
(Multiple Choice)
4.8/5
(33)
Low-cost, realistic, efficient methods for completing an activity under normal conditions are supported by ____ time.
(Multiple Choice)
4.9/5
(34)
According to Brooks' Law, adding more people to a late project is most likely to have which of the following impact?
(Multiple Choice)
4.8/5
(39)
Direct costs are so named because they can be assigned directly to a work package and activity.
(True/False)
4.9/5
(37)
Given that an activity's normal time and cost are ten days and $400, and its crash time is five days and $800, what is the activity's slope?
(Essay)
4.8/5
(45)
To shorten the duration of a project the project manager should limit the choices of activities to just those which ________.
(Short Answer)
4.9/5
(47)
A project network is classified as sensitive if it has a large number of interacting paths.
(True/False)
4.8/5
(34)
Costs such as supervision, administration, consultants, and interest are examples of ________ project costs.
(Short Answer)
4.8/5
(30)
Intense global competition and rapid technological advances create pressure on developing projects rapidly.This is an example of reducing project duration caused by:
(Multiple Choice)
4.8/5
(38)
Which of the following is the easiest method for shortening project time?
(Multiple Choice)
4.7/5
(42)
Which of the following correctly calculates an activity's cost slope?
(Multiple Choice)
4.8/5
(32)
A positive situation where moving toward the optimum time can result in very real, large savings-this occurs when the network is:
(Multiple Choice)
4.9/5
(32)
Imposed project durations almost always leads to a higher-cost project than one planned with detailed scheduling of all the project's activities.
(True/False)
4.9/5
(38)
If a network has several critical or near-critical paths it is deemed to be:
(Multiple Choice)
4.8/5
(36)
Crashing a more expensive activity may be wise if fewer inherent risks are involved.
(True/False)
4.9/5
(35)
Which of the following is not one of the more commonly used options for cutting project costs?
(Multiple Choice)
4.8/5
(35)
Showing 21 - 40 of 94
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)