Exam 9: Reducing Project Duration
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection88 Questions
Exam 3: Organization: Structure and Culture94 Questions
Exam 4: Defining the Project89 Questions
Exam 5: Estimating Project Times and Costs91 Questions
Exam 6: Developing a Project Plan94 Questions
Exam 7: Managing Risk87 Questions
Exam 8: Scheduling Resources and Costs90 Questions
Exam 9: Reducing Project Duration94 Questions
Exam 10: Leadership: Being an Effective Project Manager88 Questions
Exam 11: Managing Project Teams94 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations94 Questions
Exam 13: Progress and Performance Measurement and Evaluation88 Questions
Exam 14: Project Closure88 Questions
Exam 15: International Projects94 Questions
Exam 16: Oversight86 Questions
Exam 17: An Introduction to Agile Project Management85 Questions
Exam 18: Project Management Career Paths35 Questions
Select questions type
According to ________, adding more manpower to a late software project makes it later.
(Short Answer)
4.9/5
(41)
The easiest way to add more labor to a project is not to add more people, but to add ___________.
(Short Answer)
4.9/5
(31)
Managers have several effective methods for crashing specific project activities when resources are not constrained.
(True/False)
4.8/5
(29)
Identify and briefly describe five reasons for attempting to reduce the duration of a project.
(Essay)
4.9/5
(44)
Incentive contracts can make reduction of project time rewarding-usually for both the project contractor and owner.
(True/False)
4.8/5
(39)
A network is considered to be ________ if it has a predominate critical path with no other path close in terms of slack.
(Short Answer)
4.7/5
(31)
The higher the slope of an activity the greater the cost to reduce its duration.
(True/False)
4.8/5
(37)
The total cost for each possible duration of a project is the sum of labor, materials, and equipment.
(True/False)
4.8/5
(36)
Collecting crash times for a moderate-size project is relatively easy.
(True/False)
4.8/5
(34)
The sum of the costs of all the work packages represents the total direct costs for the project.
(True/False)
4.9/5
(35)
Which of the following is/are included in a Project Cost-Duration Graph?
(Multiple Choice)
4.7/5
(38)
Draw a typical Project Cost-Duration Graph and label the key elements.
(Short Answer)
4.8/5
(30)
An activity's ________ is calculated by dividing the rise by the run.
(Short Answer)
4.9/5
(38)
The most common response for meeting unattainable deadlines is to
(Multiple Choice)
4.9/5
(37)
Given an equal level of risk and the need to reduce overall project duration, why would you not select the activity with the lowest slope in the entire project network to crash first?
(Essay)
4.9/5
(41)
Identify options for accelerating a project schedule when resources are constrained or the budget is severely constrained.
(Essay)
4.9/5
(31)