Exam 6: Developing a Project Plan
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection88 Questions
Exam 3: Organization: Structure and Culture94 Questions
Exam 4: Defining the Project89 Questions
Exam 5: Estimating Project Times and Costs91 Questions
Exam 6: Developing a Project Plan94 Questions
Exam 7: Managing Risk87 Questions
Exam 8: Scheduling Resources and Costs90 Questions
Exam 9: Reducing Project Duration94 Questions
Exam 10: Leadership: Being an Effective Project Manager88 Questions
Exam 11: Managing Project Teams94 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations94 Questions
Exam 13: Progress and Performance Measurement and Evaluation88 Questions
Exam 14: Project Closure88 Questions
Exam 15: International Projects94 Questions
Exam 16: Oversight86 Questions
Exam 17: An Introduction to Agile Project Management85 Questions
Exam 18: Project Management Career Paths35 Questions
Select questions type
___________ reflects the likelihood the original critical path(s) will change once the project is initiated.
(Short Answer)
4.7/5
(33)
The ________ approach to creating project networks has come to dominate most projects.
(Short Answer)
4.8/5
(32)
What is the Concurrent Engineering Approach and why should project managers be aware of it?
(Essay)
4.8/5
(27)
Which of the following will correctly calculate the total slack in an activity?
(Multiple Choice)
4.8/5
(37)
The minimum amount of time a dependent activity must be delayed to begin or end is referred to as:
(Multiple Choice)
4.7/5
(37)
Different activities along the same path can have different total slack.
(True/False)
4.8/5
(46)
A (n) ________ represents a point in time when an activity is started or completed and does not consume time.
(Short Answer)
4.9/5
(43)
An activity is on the critical path if its ________ is the lowest in the network.
(Short Answer)
4.8/5
(32)
An AON project network uses which of the following basic building blocks?
(Multiple Choice)
4.8/5
(35)
The critical path is the shortest path through a network and indicates activities that cannot be delayed without delaying the project.
(True/False)
4.9/5
(25)
Using a special color copy machine for a tradeshow publication illustrates the concept of
(Multiple Choice)
4.9/5
(29)
Which of the following correctly calculates the early finish for an activity?
(Multiple Choice)
4.9/5
(38)
A sequence of connected, dependent activities is termed a(n)
(Multiple Choice)
4.9/5
(36)
A/an _________ activity has more than one dependency arrow flowing from it.
(Multiple Choice)
4.8/5
(32)