Exam 6: Developing a Project Plan

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

What are the eight rules to follow in developing project networks?

(Essay)
4.8/5
(33)

___________ reflects the likelihood the original critical path(s) will change once the project is initiated.

(Short Answer)
4.7/5
(33)

What is total slack and how do you determine it?

(Essay)
4.7/5
(32)

In a project network, ________ indicate precedence and flow.

(Short Answer)
5.0/5
(39)

The ________ approach to creating project networks has come to dominate most projects.

(Short Answer)
4.8/5
(32)

An activity includes only one work package.

(True/False)
4.9/5
(32)

What is the Concurrent Engineering Approach and why should project managers be aware of it?

(Essay)
4.8/5
(27)

Which of the following will correctly calculate the total slack in an activity?

(Multiple Choice)
4.8/5
(37)

The minimum amount of time a dependent activity must be delayed to begin or end is referred to as:

(Multiple Choice)
4.7/5
(37)

By definition, the critical path always has zero slack.

(True/False)
4.7/5
(41)

Different activities along the same path can have different total slack.

(True/False)
4.8/5
(46)

A (n) ________ represents a point in time when an activity is started or completed and does not consume time.

(Short Answer)
4.9/5
(43)

An activity is on the critical path if its ________ is the lowest in the network.

(Short Answer)
4.8/5
(32)

An AON project network uses which of the following basic building blocks?

(Multiple Choice)
4.8/5
(35)

The critical path is the shortest path through a network and indicates activities that cannot be delayed without delaying the project.

(True/False)
4.9/5
(25)

Using a special color copy machine for a tradeshow publication illustrates the concept of

(Multiple Choice)
4.9/5
(29)

Concurrent engineering is a good example of good use of

(Multiple Choice)
5.0/5
(28)

Which of the following correctly calculates the early finish for an activity?

(Multiple Choice)
4.9/5
(38)

A sequence of connected, dependent activities is termed a(n)

(Multiple Choice)
4.9/5
(36)

A/an _________ activity has more than one dependency arrow flowing from it.

(Multiple Choice)
4.8/5
(32)
Showing 41 - 60 of 94
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)