Exam 6: Developing a Project Plan
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection88 Questions
Exam 3: Organization: Structure and Culture94 Questions
Exam 4: Defining the Project89 Questions
Exam 5: Estimating Project Times and Costs91 Questions
Exam 6: Developing a Project Plan94 Questions
Exam 7: Managing Risk87 Questions
Exam 8: Scheduling Resources and Costs90 Questions
Exam 9: Reducing Project Duration94 Questions
Exam 10: Leadership: Being an Effective Project Manager88 Questions
Exam 11: Managing Project Teams94 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations94 Questions
Exam 13: Progress and Performance Measurement and Evaluation88 Questions
Exam 14: Project Closure88 Questions
Exam 15: International Projects94 Questions
Exam 16: Oversight86 Questions
Exam 17: An Introduction to Agile Project Management85 Questions
Exam 18: Project Management Career Paths35 Questions
Select questions type
Identify and discuss the two major reasons for the integration of work packages into the project network failing in actual practice.
(Essay)
4.8/5
(35)
What are the two approaches used to develop project networks and identify the differences between them?
(Essay)
4.8/5
(33)
In developing a project network, neither looping statements nor conditional statements are permitted.
(True/False)
4.7/5
(34)
The two approaches used to develop project networks are AOA and AON.
(True/False)
4.8/5
(35)
Lags can be use to constrain the start and finish of an activity.
(True/False)
4.9/5
(34)
What is a Gantt chart and what advantages does it have over project networks?
(Essay)
4.8/5
(27)
If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?
(Multiple Choice)
4.8/5
(35)
The forward pass in project network calculations determines the
(Multiple Choice)
4.7/5
(29)
In the network computation process what is a forward pass and what three things does it determine?
(Essay)
4.7/5
(37)
An activity that has more than one dependency arrow flowing into it is termed a(n)
(Multiple Choice)
4.8/5
(40)
Activities that must occur immediately before a given activity are called ________ activities.
(Short Answer)
4.8/5
(40)
The amount of time an activity can be delayed and yet not delay the project is termed
(Multiple Choice)
4.9/5
(33)
Activities that must immediately follow a given activity are called ________ activities.
(Short Answer)
4.8/5
(40)
On a project network, the activity times are derived from the
(Multiple Choice)
4.8/5
(34)
Information to develop a project network is collected from the
(Multiple Choice)
4.9/5
(33)
Which of the following correctly calculates the late start for an activity?
(Multiple Choice)
4.9/5
(38)
________ activities must be completed immediately before a particular activity.
(Multiple Choice)
4.9/5
(28)