Exam 6: Developing a Project Plan

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Identify and discuss the two major reasons for the integration of work packages into the project network failing in actual practice.

(Essay)
4.8/5
(35)

What are the two approaches used to develop project networks and identify the differences between them?

(Essay)
4.8/5
(33)

In developing a project network, neither looping statements nor conditional statements are permitted.

(True/False)
4.7/5
(34)

The two approaches used to develop project networks are AOA and AON.

(True/False)
4.8/5
(35)

Lags can be use to constrain the start and finish of an activity.

(True/False)
4.9/5
(34)

What is a Gantt chart and what advantages does it have over project networks?

(Essay)
4.8/5
(27)

Typically an activity on a project network represents

(Multiple Choice)
4.9/5
(45)

If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?

(Multiple Choice)
4.8/5
(35)

The forward pass in project network calculations determines the

(Multiple Choice)
4.7/5
(29)

In the network computation process what is a forward pass and what three things does it determine?

(Essay)
4.7/5
(37)

An activity that has more than one dependency arrow flowing into it is termed a(n)

(Multiple Choice)
4.8/5
(40)

Arrows on an AON project network represent:

(Multiple Choice)
4.9/5
(41)

Activities that must occur immediately before a given activity are called ________ activities.

(Short Answer)
4.8/5
(40)

The amount of time an activity can be delayed and yet not delay the project is termed

(Multiple Choice)
4.9/5
(33)

Activities that must immediately follow a given activity are called ________ activities.

(Short Answer)
4.8/5
(40)

On a project network, the activity times are derived from the

(Multiple Choice)
4.8/5
(34)

Information to develop a project network is collected from the

(Multiple Choice)
4.9/5
(33)

Which of the following correctly calculates the late start for an activity?

(Multiple Choice)
4.9/5
(38)

________ activities must be completed immediately before a particular activity.

(Multiple Choice)
4.9/5
(28)

A (n) ________ has more than one successor activity.

(Short Answer)
4.8/5
(37)
Showing 21 - 40 of 94
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)