Exam 6: Developing a Project Plan

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Lags are used to break larger activities into smaller segments so that activities that follow can be started earlier.

(True/False)
4.8/5
(29)

What is the laddering approach to project networks and why would you use this approach?

(Essay)
4.8/5
(41)

The forward pass through a project network determines the critical path.

(True/False)
4.8/5
(39)

____________ is defined as the difference between the EF of an activity and the ES of the activity that follows it.

(Short Answer)
4.8/5
(29)

The ________ method for creating project networks is sometimes called the Precedence Diagram Method.

(Short Answer)
4.8/5
(38)

The _________ lag is the most typical type of lag that is encountered in developing networks.

(Short Answer)
4.8/5
(35)

Part of a project is to Develop Product Specifications.This is best classified as a(n)

(Multiple Choice)
4.9/5
(34)

Activities that can occur while an activity is taking place are called ________ activities.

(Short Answer)
4.9/5
(30)

Which of the following represents an activity on an AOA project network?

(Multiple Choice)
4.9/5
(34)

In a ________ the delaying of any activity will delay the completion of the project by the same amount.

(Short Answer)
4.9/5
(39)

The activity time estimates used to build a project network are derived from ________.

(Short Answer)
4.9/5
(31)

Which company utilized concurrent engineering to design a new line of cars and in the process completed its development six months ahead of schedule?

(Multiple Choice)
4.8/5
(41)

Project network logic errors include which of the following?

(Multiple Choice)
4.9/5
(36)

Activities which can take place at the same time are termed

(Multiple Choice)
4.8/5
(38)

Activities that can take place at the same time if the manager wishes them to are called ________.

(Short Answer)
5.0/5
(29)

A(n) ________ is the minimum amount of time a dependent activity must be delayed to begin or end.

(Short Answer)
4.8/5
(36)

Only activities that occur at the end of a chain of activities can have free slack.

(True/False)
4.7/5
(36)

Which of the following is not one of the basic rules to follow when developing project networks?

(Multiple Choice)
4.8/5
(31)

Identify and briefly describe the four types of lags giving an example for each type.

(Essay)
4.7/5
(36)

________ can never be negative and applies only to the last activity in a single chain of activities.

(Short Answer)
4.9/5
(45)
Showing 61 - 80 of 94
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)