A __________ activity is frequently used to identify the use of fixed resources or costs over a segment of the project.

(Short Answer)
4.9/5
(31)

Burst activities have more than one activity immediately following it (more than one dependency arrow flowing from it).

(True/False)
4.8/5
(41)

In a project network, ________ (recycling through a set of activities) is not permitted.

(Short Answer)
4.8/5
(38)

The WBS identifies dependencies, the sequencing of activities, and the timing of activities.

(True/False)
4.8/5
(27)

The backward pass in project network calculations determines the

(Multiple Choice)
4.8/5
(37)

What is a lag and why would you need to use one?

(Essay)
4.9/5
(38)

A(n) ________ is an element in the project that consumes time.

(Short Answer)
4.8/5
(36)

It is possible to have more than one critical path at the same time.

(True/False)
4.9/5
(37)

If testing cannot be completed any earlier than four days after the prototype is built, which of the following type of lag exists?

(Multiple Choice)
4.9/5
(28)

In developing a project network, each activity should have a unique identification number that is smaller than the identification numbers of activities that follow it.

(True/False)
4.7/5
(29)

When translated into a project network, a work package will become

(Multiple Choice)
4.8/5
(32)

In the network computation process what is a backward pass and what four things does it determine?

(Essay)
4.8/5
(32)

In an AOA network an activity is represented by a box.

(True/False)
4.8/5
(42)

________ activities are to be completed immediately following a particular activity.

(Multiple Choice)
4.8/5
(34)