Exam 6: Developing a Project Plan
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection88 Questions
Exam 3: Organization: Structure and Culture94 Questions
Exam 4: Defining the Project89 Questions
Exam 5: Estimating Project Times and Costs91 Questions
Exam 6: Developing a Project Plan94 Questions
Exam 7: Managing Risk87 Questions
Exam 8: Scheduling Resources and Costs90 Questions
Exam 9: Reducing Project Duration94 Questions
Exam 10: Leadership: Being an Effective Project Manager88 Questions
Exam 11: Managing Project Teams94 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations94 Questions
Exam 13: Progress and Performance Measurement and Evaluation88 Questions
Exam 14: Project Closure88 Questions
Exam 15: International Projects94 Questions
Exam 16: Oversight86 Questions
Exam 17: An Introduction to Agile Project Management85 Questions
Exam 18: Project Management Career Paths35 Questions
Select questions type
A __________ activity is frequently used to identify the use of fixed resources or costs over a segment of the project.
(Short Answer)
4.9/5
(31)
Burst activities have more than one activity immediately following it (more than one dependency arrow flowing from it).
(True/False)
4.8/5
(41)
In a project network, ________ (recycling through a set of activities) is not permitted.
(Short Answer)
4.8/5
(38)
The WBS identifies dependencies, the sequencing of activities, and the timing of activities.
(True/False)
4.8/5
(27)
The backward pass in project network calculations determines the
(Multiple Choice)
4.8/5
(37)
A(n) ________ is an element in the project that consumes time.
(Short Answer)
4.8/5
(36)
It is possible to have more than one critical path at the same time.
(True/False)
4.9/5
(37)
If testing cannot be completed any earlier than four days after the prototype is built, which of the following type of lag exists?
(Multiple Choice)
4.9/5
(28)
In developing a project network, each activity should have a unique identification number that is smaller than the identification numbers of activities that follow it.
(True/False)
4.7/5
(29)
When translated into a project network, a work package will become
(Multiple Choice)
4.8/5
(32)
In the network computation process what is a backward pass and what four things does it determine?
(Essay)
4.8/5
(32)
________ activities are to be completed immediately following a particular activity.
(Multiple Choice)
4.8/5
(34)
Showing 81 - 94 of 94
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)