Exam 4: Defining the Project
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection88 Questions
Exam 3: Organization: Structure and Culture94 Questions
Exam 4: Defining the Project89 Questions
Exam 5: Estimating Project Times and Costs91 Questions
Exam 6: Developing a Project Plan94 Questions
Exam 7: Managing Risk87 Questions
Exam 8: Scheduling Resources and Costs90 Questions
Exam 9: Reducing Project Duration94 Questions
Exam 10: Leadership: Being an Effective Project Manager88 Questions
Exam 11: Managing Project Teams94 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations94 Questions
Exam 13: Progress and Performance Measurement and Evaluation88 Questions
Exam 14: Project Closure88 Questions
Exam 15: International Projects94 Questions
Exam 16: Oversight86 Questions
Exam 17: An Introduction to Agile Project Management85 Questions
Exam 18: Project Management Career Paths35 Questions
Select questions type
Reviews with customers only refers to projects with external customers who are paying for the project.
(True/False)
4.8/5
(36)
The agreement that training will be the responsibility of the customer is an example of a project ________.
(Short Answer)
4.7/5
(36)
Significant events in a project that occur at a specific point in time, are natural control points, and are easily recognized by project participants are known as ___________.
(Short Answer)
4.7/5
(38)
In a work breakdown structure the ________ is the focal point because all budgets, work assignments, time, cost, and technical performance come together at that point.
(Short Answer)
4.7/5
(38)
The tendency for the project deliverables to expand over time-usually by changing requirements, specifications, and priorities-is called:
(Multiple Choice)
4.7/5
(32)
The purposes of the ____________ are to provide a framework to summarize organization unit work performance, identify organization units responsible for work packages, and tie the organizational unit to cost control accounts.
(Short Answer)
4.9/5
(42)
The development of a work breakdown structure with appropriate dates and budget is usually accomplished in a single iteration.
(True/False)
5.0/5
(30)
The most commonly used scheme for coding the work breakdown structure is to use a department project number assigned by the accounting department.
(True/False)
4.8/5
(33)
What is meant by "Scope Creep" and why is it significant to project managers?
(Essay)
4.9/5
(34)