Exam 9: Project Management
Exam 1: Operations Management63 Questions
Exam 2: Quality Management71 Questions
Exam 3: Statistical Quality Control111 Questions
Exam 4: Product Design75 Questions
Exam 5: Service Design79 Questions
Exam 6: Processes and Technology61 Questions
Exam 17: Scheduling80 Questions
Exam 7: Capacity and Facilities83 Questions
Exam 8: Human Resources79 Questions
Exam 9: Project Management85 Questions
Exam 10: Supply Chain Management: Strategy and Design56 Questions
Exam 11: Global Supply Chain Procurement and Distribution69 Questions
Exam 12: Forecasting85 Questions
Exam 13: Inventory Management78 Questions
Exam 13: Operational Decision-Making Tools: Simulation22 Questions
Exam 14: Operational Decision-Making Tools: Linear Programming29 Questions
Exam 14: The Sales and Operations Planning Process76 Questions
Exam 15: Resource Planning82 Questions
Exam 16: Lean Systems79 Questions
Exam 18: Operational Decision-Making Tools: Decision Analysis38 Questions
Exam 19: Operational Decision-Making Tools: Acceptance Sampling28 Questions
Exam 20: Decision-Making Tools: Facility Location Models23 Questions
Exam 21: Operational Decision-Making Tools: Work Measurement31 Questions
Select questions type
The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project.
Table 9.2
-Using Table 9.2,the variance for activity E is

(Multiple Choice)
4.8/5
(30)
The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project.
Table 9.2
-Using Table 9.2,the probability that the project could be completed in 34 weeks or less is approximately

(Multiple Choice)
4.9/5
(43)
Why have projects taken on a more crucial role in operations management?
(Essay)
4.7/5
(34)
In project management the term slack refers to the amount of time
(Multiple Choice)
4.9/5
(44)
In general,crashing costs decrease as a project's duration is shortened.
(True/False)
4.8/5
(44)
The critical path is the shortest path through the project's network.
(True/False)
4.9/5
(35)
The estimated variance for an activity with a most likely time (m)equal to 12 weeks,an optimistic time (a)equal to 9 weeks,and a pessimistic time (b)equal to 18 weeks is
(Multiple Choice)
4.8/5
(24)
Enterprise project management refers to the management and control of a large,complex project.
(True/False)
4.7/5
(40)
A work breakdown structure provides a common understanding of and justification for a project.
(True/False)
4.9/5
(36)
The upper level of a work breakdown structure for a project highlights summary activities and/or major components.
(True/False)
4.8/5
(32)
A unique,one-time operational activity or effort is referred to as a process.
(True/False)
4.9/5
(37)
Two key elements of project control are time management and cost management.
(True/False)
4.8/5
(34)
A standard procedure for numerically measuring a project's progress is referred to as a(n)
(Multiple Choice)
4.8/5
(40)
The three major components of project management include planning,scheduling,and costing.
(True/False)
4.9/5
(45)
A bar graph displaying when activities are scheduled to start,when they will be finished,and where extra time is available is known as a
(Multiple Choice)
4.9/5
(34)
The _______________ probability distribution is typically used to describe uncertain activity times in a project.
(Multiple Choice)
4.7/5
(38)
Slack represents the amount of time an activity can be delayed without delaying the project completion time.
(True/False)
4.7/5
(38)
Which of the following statements is generally true regarding the relationship between project crashing costs and indirect costs?
(Multiple Choice)
5.0/5
(37)
In general,the latest finish time for an activity is equal to
(Multiple Choice)
4.7/5
(38)
The estimated variance for an activity with a most likely time (m)equal to 11 days,the optimistic time (a)equal to 6 days ,and the pessimistic time (b)equal to 18 days is
(Multiple Choice)
4.9/5
(35)
Showing 41 - 60 of 85
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)