Exam 9: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project. The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the variance for activity E is Table 9.2 -Using Table 9.2,the variance for activity E is

(Multiple Choice)
4.8/5
(30)

The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project. The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the probability that the project could be completed in 34 weeks or less is approximately Table 9.2 -Using Table 9.2,the probability that the project could be completed in 34 weeks or less is approximately

(Multiple Choice)
4.9/5
(43)

Why have projects taken on a more crucial role in operations management?

(Essay)
4.7/5
(34)

In project management the term slack refers to the amount of time

(Multiple Choice)
4.9/5
(44)

In general,crashing costs decrease as a project's duration is shortened.

(True/False)
4.8/5
(44)

The critical path is the shortest path through the project's network.

(True/False)
4.9/5
(35)

The estimated variance for an activity with a most likely time (m)equal to 12 weeks,an optimistic time (a)equal to 9 weeks,and a pessimistic time (b)equal to 18 weeks is

(Multiple Choice)
4.8/5
(24)

Enterprise project management refers to the management and control of a large,complex project.

(True/False)
4.7/5
(40)

A work breakdown structure provides a common understanding of and justification for a project.

(True/False)
4.9/5
(36)

The upper level of a work breakdown structure for a project highlights summary activities and/or major components.

(True/False)
4.8/5
(32)

A unique,one-time operational activity or effort is referred to as a process.

(True/False)
4.9/5
(37)

Two key elements of project control are time management and cost management.

(True/False)
4.8/5
(34)

A standard procedure for numerically measuring a project's progress is referred to as a(n)

(Multiple Choice)
4.8/5
(40)

The three major components of project management include planning,scheduling,and costing.

(True/False)
4.9/5
(45)

A bar graph displaying when activities are scheduled to start,when they will be finished,and where extra time is available is known as a

(Multiple Choice)
4.9/5
(34)

The _______________ probability distribution is typically used to describe uncertain activity times in a project.

(Multiple Choice)
4.7/5
(38)

Slack represents the amount of time an activity can be delayed without delaying the project completion time.

(True/False)
4.7/5
(38)

Which of the following statements is generally true regarding the relationship between project crashing costs and indirect costs?

(Multiple Choice)
5.0/5
(37)

In general,the latest finish time for an activity is equal to

(Multiple Choice)
4.7/5
(38)

The estimated variance for an activity with a most likely time (m)equal to 11 days,the optimistic time (a)equal to 6 days ,and the pessimistic time (b)equal to 18 days is

(Multiple Choice)
4.9/5
(35)
Showing 41 - 60 of 85
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)