Exam 10: Layout Strategies
Exam 1: Operations and Productivity126 Questions
Exam 2: Operations Strategy in a Global Environment119 Questions
Exam 3: Project Management120 Questions
Exam 4: Forecasting141 Questions
Exam 5: Design of Goods and Services118 Questions
Exam 6: Managing Quality123 Questions
Exam 7: Process Strategy108 Questions
Exam 8: Capacity and Constraint Management96 Questions
Exam 9: Location Strategies120 Questions
Exam 10: Layout Strategies146 Questions
Exam 11: Human Resources, job Design, and Work Measurement154 Questions
Exam 12: Supply Chain Management144 Questions
Exam 13: Inventory Management163 Questions
Exam 14: Aggregate Planning and Sop116 Questions
Exam 15: Material Requirements Planning Mrpand Erp113 Questions
Exam 16: Short-Term Scheduling116 Questions
Exam 17: Jit, tps, and Lean Operations115 Questions
Exam 18: Maintenance and Reliability111 Questions
Exam 19: Sustainability in the Supply Chain80 Questions
Exam 20: Statistical Process Control144 Questions
Exam 21: Supply Chain Management Analytics55 Questions
Exam 22: Decision-Making Tools97 Questions
Exam 23: Linear Programming80 Questions
Exam 24: Transportation Models89 Questions
Exam 25: Waiting-Line Models119 Questions
Exam 26: Learning Curves105 Questions
Exam 27: Simulation75 Questions
Select questions type
Four hundred and eighty minutes of production time are available per day.Scheduled production is 120 units per day.What is the required cycle time?
(Multiple Choice)
4.9/5
(36)
A product-oriented layout would be MOST appropriate for which one of the following businesses?
(Multiple Choice)
4.8/5
(37)
The ________ layout's main objective is to equalize the task time for each station.
(Multiple Choice)
4.8/5
(33)
________ is the pace (frequency)of production necessary (time per unit)to meet customer orders.
(Short Answer)
4.8/5
(33)
An assembly line consists of 21 tasks grouped into 5 workstations.The sum of the 21 task times is 85 minutes.The largest assigned cycle time is 20 minutes.What is the efficiency of this line?
(Multiple Choice)
4.9/5
(48)
Which of the following is NOT an information requirement for solving a load-distance problem to design a process layout?
(Multiple Choice)
4.7/5
(36)
A firm operates a flow shop building kitchen cabinetry for recreational vehicles.The major activities of this process are listed below.
a.Draw the appropriate network for this project.
b.What would the cycle time be if the goal is to produce 20 units per month (the plant operates
160 hours per month)?
c.What is the theoretical minimum number of workstations needed?
d.Balance with the most following tasks heuristic.What tasks are assigned to which stations?
e.What is the efficiency of the line obtained in part d?

(Essay)
4.9/5
(37)
Which of the following is NOT one of the factors complicating the techniques for addressing the fixed-position layout?
(Multiple Choice)
4.9/5
(38)
________ avoids placing materials or supplies in storage by processing them as they are received for shipment.
(Short Answer)
4.8/5
(32)
An assembly line has been designed to make battery-powered beverage mixers.Task details are shown in the table below:
a.What is the assigned cycle time (in minutes)?
b.What is the maximum output rate of this line in mixers per hour?
c.What is the total idle time per cycle?
d.What is the assembly line's efficiency?

(Essay)
4.8/5
(29)
Four hundred and eighty minutes of production time are available per day.The schedule calls for the production of 80 units per day.Each unit of the product requires 30 minutes of work.What is the theoretical minimum number of workstations?
(Multiple Choice)
4.7/5
(41)
An assembly line consists of 158 tasks grouped into 32 workstations.The sum of all task times is 105 minutes.The largest assigned cycle time is 4 minutes.What is the efficiency of this line?
(Multiple Choice)
4.9/5
(37)
Servicescape refers to the physical surrounding in which the service is delivered.
(True/False)
4.9/5
(48)
One guideline for determining the arrangement and space allocation of a retail store is to place high-impulse and high-margin items in prominent locations.
(True/False)
4.9/5
(35)
An assembly line is assigned as follows.Station 1- task A,B,and C.Station 2- task D.Station 3- task E and F.The task times are 7,3,2,9,4,and 5 minutes respective to A,B,C,D,E,and F.(Assume that there is no precedence relationships between the tasks,i.e.they can be performed in any order)
(a)Calculate the efficiency.
(b)What would the assignment of tasks to stations be using the shortest processing time heuristic (assuming the current maximum station time remains the cycle time)?
(Essay)