Exam 26: Learning Curves
Exam 1: Operations and Productivity129 Questions
Exam 2: Operations Strategy in a Global Environment120 Questions
Exam 3: Project Management124 Questions
Exam 4: Forecasting141 Questions
Exam 5: Design of Goods and Services121 Questions
Exam 6: Managing Quality125 Questions
Exam 7: Process Strategy113 Questions
Exam 8: Location Strategies121 Questions
Exam 9: Layout Strategies146 Questions
Exam 10: Human Resources,job Design,and Work Measurement159 Questions
Exam 11: Supply Chain Management145 Questions
Exam 12: Inventory Management165 Questions
Exam 13: Aggregate Planning and Sop116 Questions
Exam 14: Material Requirements Planning Mrpand ERP113 Questions
Exam 15: Short-Term Scheduling116 Questions
Exam 16: Lean Operations116 Questions
Exam 17: Maintenance and Reliability114 Questions
Exam 18: Sustainability in the Supply Chain84 Questions
Exam 19: Statistical Process Control144 Questions
Exam 20: Capacity and Constraint Management101 Questions
Exam 21: Supply Chain Management Analytics67 Questions
Exam 22: Decision-Making Tools100 Questions
Exam 23: Linear Programming98 Questions
Exam 24: Transportation Models89 Questions
Exam 25: Waiting-Line Models119 Questions
Exam 26: Learning Curves110 Questions
Exam 27: Simulation75 Questions
Select questions type
If the learning curve for a process is 80 percent,that same process has a 20 percent ________.
(Essay)
4.8/5
(37)
The learning rate for a product is 90 percent.The first unit took 10 hours to complete.The manufacturer wants to determine how many hours the fourth unit will take by using the formula approach.What is the coefficient b for that calculation?
(Multiple Choice)
4.8/5
(35)
Companies pursuing a learning curve strategy MUST increase which of the following?
(Multiple Choice)
4.9/5
(32)
Which of the following statements regarding the usefulness of learning curves is FALSE?
(Multiple Choice)
4.8/5
(39)
Your firm has expertise with a special type of hand-finished furniture.The learning curve is known to be 82%.If the first piece of furniture took 6 hours,estimate (using the doubling approach)how long it will take to complete the third unit.
(Essay)
4.8/5
(36)
What problems in scheduling can arise if adjustments for learning curve effects in operations are not made?
(Essay)
4.9/5
(29)
The first unit took 10 hours and the eighth unit took 1.25 hours.What is the learning curve?
(Multiple Choice)
4.9/5
(36)
Your firm has a contract to make 20 specialty lenses for night vision equipment.The first one took 40 hours.Learning is expected at the 85% learning curve.How long will it take to finish all 20 units?
(Essay)
4.8/5
(32)
When comparing a 70% learning curve versus a 90% learning curve,which one results in a more rapid reduction in labor requirements? Why?
(Essay)
4.7/5
(39)
A defense contractor has just started producing turbines for a new government contract.The first turbine took 7000 hours to produce.If the learning curve is 90%,how long will it take to produce the 10th turbine? (Use at least three decimals in the exponent if you use the formula approach. )
(Multiple Choice)
4.8/5
(38)
The first unit took 10 hours and the fourth unit 8.1 hours.What is the improvement rate?
(Multiple Choice)
4.7/5
(26)
The first unit took 79 hours;the tenth took 46 hours.What learning curve is implied by the data?
(Essay)
4.7/5
(35)
If the first unit in a series of units takes 200 days to complete,and the learning curve is 80%,then the second unit will take 160 days.
(True/False)
4.8/5
(36)
The first unit of production took 10 hours with an 80% learning curve.How long will it take to complete both the first and second units?
(Multiple Choice)
5.0/5
(39)
A product was priced assuming an 80% learning curve.How much extra labor (in $)will be required on the 4th product if the learning curve is actually 90%? Assume that the first unit cost $100 to produce.
(Essay)
4.9/5
(37)
The learning curve for a product is 80 percent.The first unit took 100 hours to complete.The manufacturer wants to determine how many hours the fifth unit will take by using the formula approach.What is the coefficient b for that calculation?
(Multiple Choice)
4.8/5
(28)
"By tradition,learning curves are defined in terms of the complements of their improvement rates." Explain.
(Essay)
4.8/5
(25)
In the formula approach to learning curve calculations,you have used the formula TN = T1 (Nb).Your manager shows you a problem for which b is specified as -.18443.What learning curve does that value represent?
(Essay)
4.8/5
(28)
The first unit of a product took 832 hours to build,and the learning curve is 75%.How long will it take to make the 30th unit? (Use at least three decimals in the exponent if you use the formula approach. )