Exam 9: Layout Strategies
Exam 1: Operations and Productivity127 Questions
Exam 2: Operations Strategy in a Global Environment119 Questions
Exam 3: Project Management120 Questions
Exam 4: Forecasting141 Questions
Exam 5: Design of Goods and Services118 Questions
Exam 6: Managing Quality127 Questions
Exam 7: Process Strategy108 Questions
Exam 8: Location Strategies120 Questions
Exam 9: Layout Strategies145 Questions
Exam 10: Human Resources,job Design,and Work Measurement154 Questions
Exam 11: Supply Chain Management145 Questions
Exam 12: Inventory Management163 Questions
Exam 13: Aggregate Planning and Sop116 Questions
Exam 14: Material Requirements Planning Mrpand Erp116 Questions
Exam 15: Short-Term Scheduling115 Questions
Exam 16: Jit,tps,and Lean Operations115 Questions
Exam 17: Maintenance and Reliability111 Questions
Exam 18: Sustainability in the Supply Chain80 Questions
Exam 19: Statistical Process Control144 Questions
Exam 20: Capacity and Constraint Management96 Questions
Exam 21: Supply Chain Management Analytics55 Questions
Exam 22: Decision-Making Tools96 Questions
Exam 23: Linear Programming88 Questions
Exam 24: Transportation Models89 Questions
Exam 25: Waiting-Line Models119 Questions
Exam 26: Learning Curves110 Questions
Exam 27: Simulation74 Questions
Select questions type
One guideline for a retail layout is to locate high-draw items around the periphery of the store.
(True/False)
4.7/5
(39)
The major problem addressed by the warehouse layout strategy is:
(Multiple Choice)
4.8/5
(25)
Which of the following reduces product handling,inventory,and facility costs,but requires both (1)tight scheduling and (2)accurate inbound product information?
(Multiple Choice)
4.8/5
(29)
An airport is trying to balance where to place the three subgroups (local (A),regional (B),and national (C))for an airline.The distance between terminals and the number of trips that travelers make between subgroups for flight connections per day are listed.Find the assignment that minimizes the distance travelers must walk.


(Essay)
4.9/5
(44)
________ refers to the physical surroundings in which a service takes place,and how they affect customers and employees.
(Essay)
4.8/5
(35)
Four hundred and eighty minutes of production time are available per day.The schedule calls for the production of 80 units per day.Each unit of the product requires 30 minutes of work.What is the theoretical minimum number of workstations?
(Multiple Choice)
4.8/5
(52)
________ is the maximum time that the product is allowed at each workstation.
(Essay)
4.7/5
(31)
A firm operates a flow shop building kitchen cabinetry for recreational vehicles.The major activities of this process are listed below.
a.Draw the appropriate network for this project.
b.What would the cycle time be if the goal is to produce 20 units per month (the plant operates
160 hours per month)?
c.What is the theoretical minimum number of workstations needed?
d.Balance with the most following tasks heuristic.What tasks are assigned to which stations?
e.What is the efficiency of the line obtained in part d?

(Essay)
4.9/5
(36)
Departments A,B,C,and D need to be assigned to four rooms 1,2,3,and 4.These rooms are arranged in a row,in that order,with 20 meters between each.The departmental work flows are contained in the table below.
(a)What is the material handling total of assigning A-1,B-2,C-3,D-4?
(b)What is the material handling total of assigning A-1,B-3,C-4,D-2?


(Essay)
4.8/5
(33)
Workspace can inspire informal and productive encounters if it balances what three physical and social aspects?
(Multiple Choice)
4.9/5
(36)
One of the major advantages of process-oriented layouts is:
(Multiple Choice)
4.7/5
(36)
What design guidelines help retail layouts to maximize customer exposure to products?
(Essay)
4.9/5
(46)
The assumptions necessary for a successful product-oriented layout include all EXCEPT which of the following?
(Multiple Choice)
4.8/5
(39)
Which of the following does NOT support the retail layout objective of maximizing customer exposure to products?
(Multiple Choice)
4.8/5
(38)
A product-oriented layout would be MOST appropriate for which one of the following businesses?
(Multiple Choice)
4.8/5
(35)
One drawback of a product-oriented layout is that work stoppage at any one point ties up the whole operation.
(True/False)
4.7/5
(47)
What is a servicescape? How is it related to the retail layout problem? What are the three elements of servicescape for dealing with these human issues?
(Essay)
4.9/5
(39)
The work cell layout,a special arrangement of machinery and personnel to focus on the production of a single product or group of related products,is for manufacturing applications and has no relevance to services.
(True/False)