Exam 9: Layout Strategies
Exam 1: Operations and Productivity127 Questions
Exam 2: Operations Strategy in a Global Environment119 Questions
Exam 3: Project Management120 Questions
Exam 4: Forecasting141 Questions
Exam 5: Design of Goods and Services118 Questions
Exam 6: Managing Quality127 Questions
Exam 7: Process Strategy108 Questions
Exam 8: Location Strategies120 Questions
Exam 9: Layout Strategies145 Questions
Exam 10: Human Resources,job Design,and Work Measurement154 Questions
Exam 11: Supply Chain Management145 Questions
Exam 12: Inventory Management163 Questions
Exam 13: Aggregate Planning and Sop116 Questions
Exam 14: Material Requirements Planning Mrpand Erp116 Questions
Exam 15: Short-Term Scheduling115 Questions
Exam 16: Jit,tps,and Lean Operations115 Questions
Exam 17: Maintenance and Reliability111 Questions
Exam 18: Sustainability in the Supply Chain80 Questions
Exam 19: Statistical Process Control144 Questions
Exam 20: Capacity and Constraint Management96 Questions
Exam 21: Supply Chain Management Analytics55 Questions
Exam 22: Decision-Making Tools96 Questions
Exam 23: Linear Programming88 Questions
Exam 24: Transportation Models89 Questions
Exam 25: Waiting-Line Models119 Questions
Exam 26: Learning Curves110 Questions
Exam 27: Simulation74 Questions
Select questions type
Which of the statements below best describes office layout?
(Multiple Choice)
4.9/5
(40)
The ________ layout's main objective is to equalize the task time for each station.
(Multiple Choice)
4.9/5
(37)
Which of the following is one of the main advantages of a product-oriented layout?
(Multiple Choice)
4.7/5
(45)
What are the advantages and disadvantages of product-oriented layouts?
(Essay)
4.8/5
(40)
The biggest advantage of a product layout is its flexibility to handle a varied product mix.
(True/False)
4.9/5
(43)
Utilization of the total "cube" is the dominant consideration in office layout.
(True/False)
4.8/5
(47)
Which of the following is NOT an information requirement for solving a load-distance problem to design a process layout?
(Multiple Choice)
4.8/5
(35)
A(n)________ line is a machine-paced product-oriented facility for building components.
(Essay)
4.7/5
(38)
The ________ uses non-numeric "closeness" ratings to determine which departments should be located near one another and which departments should be kept farther apart.
(Essay)
4.9/5
(40)
A company is designing a product layout for a new product.It plans to use this production line eight hours a day in order to meet a schedule of 400 units per day.The tasks necessary to produce this product are detailed in the table below.
a.Draw the network described in the table.
b.Without regard to a production schedule,what is the minimum possible cycle time (in seconds)for this situation;what is the maximum?
c.What is the required cycle time (in seconds)in order to meet the schedule?
d.What is the theoretical minimum number of workstations needed to meet the schedule?
e.Balance this line using longest processing time.
f.What is the efficiency of the balance obtained in part e?

(Essay)
4.9/5
(39)
Briefly explain what "slotting" is.What ethical issues might arise with regard to slotting?
(Essay)
4.9/5
(41)
One guideline for determining the arrangement and space allocation of a retail store is to place high-impulse and high-margin items in prominent locations.
(True/False)
4.9/5
(39)
Identify the five common layout heuristics used to assign tasks to workstations in assembly-line balancing.
(Essay)
4.9/5
(39)
Which of the following is a common heuristic for assembly line balancing?
(Multiple Choice)
4.7/5
(46)
________ layouts deal with low-volume,high-variety production with like machines and equipment grouped together.
(Essay)
4.9/5
(28)
In a product-oriented layout,what is the process of deciding how to assign tasks to workstations?
(Multiple Choice)
4.9/5
(39)
Develop a solution for the following line balancing problem,allowing a cycle time of 5 minutes.
a.Draw the precedence diagram for the set of tasks.
b.Calculate the theoretical minimum number of workstations.
c.Balance this line using the longest task time heuristic.
d.What tasks are assigned to which stations?
e.Does the solution have the minimum number of stations? Explain.
f.How much idle time is there,summed over all workstations?
g.What is the efficiency of this line?


(Essay)
4.8/5
(51)