Exam 3: Project Management
Exam 1: Operations and Productivity127 Questions
Exam 2: Operations Strategy in a Global Environment119 Questions
Exam 3: Project Management120 Questions
Exam 4: Forecasting141 Questions
Exam 5: Design of Goods and Services118 Questions
Exam 6: Managing Quality127 Questions
Exam 7: Process Strategy108 Questions
Exam 8: Location Strategies120 Questions
Exam 9: Layout Strategies145 Questions
Exam 10: Human Resources,job Design,and Work Measurement154 Questions
Exam 11: Supply Chain Management145 Questions
Exam 12: Inventory Management163 Questions
Exam 13: Aggregate Planning and Sop116 Questions
Exam 14: Material Requirements Planning Mrpand Erp116 Questions
Exam 15: Short-Term Scheduling115 Questions
Exam 16: Jit,tps,and Lean Operations115 Questions
Exam 17: Maintenance and Reliability111 Questions
Exam 18: Sustainability in the Supply Chain80 Questions
Exam 19: Statistical Process Control144 Questions
Exam 20: Capacity and Constraint Management96 Questions
Exam 21: Supply Chain Management Analytics55 Questions
Exam 22: Decision-Making Tools96 Questions
Exam 23: Linear Programming88 Questions
Exam 24: Transportation Models89 Questions
Exam 25: Waiting-Line Models119 Questions
Exam 26: Learning Curves110 Questions
Exam 27: Simulation74 Questions
Select questions type
What are the earliest activity start time and latest activity start time,and how are they computed?
(Essay)
4.9/5
(38)
Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
a.What is the crash cost per unit time for activity A?
b.What is the crash cost per unit time for activity B?
c.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost?
d.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost?
e.Assuming no other paths become critical,how much can this project be shortened at what total added cost?

(Essay)
4.9/5
(39)
Slack is the amount of time an activity can be delayed without delaying the entire project.
(True/False)
4.7/5
(37)
Explain why the critical path is the longest,not the shortest,path through a network.
(Essay)
4.8/5
(31)
The ________ distribution is appropriate for calculating expected activity times and activity variances in PERT networks.
(Essay)
4.8/5
(27)
The shortest of all paths through the network is the critical path.
(True/False)
4.8/5
(36)
Consider the network described in the table below.
a.Calculate the expected duration of each activity.
b.Calculate the expected duration and variance of the critical path.
c.Calculate the probability that the project will be completed in fewer than 30 time units.

(Essay)
4.9/5
(48)
The ________ distribution is used by PERT analysis to calculate expected activity times and variances.
(Multiple Choice)
4.9/5
(33)
Which of the following statements regarding Bechtel is true?
(Multiple Choice)
4.9/5
(40)
Which of the following statements regarding CPM networks is true?
(Multiple Choice)
4.8/5
(31)
Project managers have their own code of ethics,established by the Project Management Institute.
(True/False)
5.0/5
(43)
The ________ has established a code of ethics especially for project managers.
(Essay)
4.9/5
(36)
The ES of an activity that has only one predecessor is simply the EF of that predecessor.
(True/False)
4.8/5
(34)
A local project being analyzed by PERT has 42 activities,13 of which are on the critical path.If the estimated time along the critical path is 105 days with a project variance of 25,what is the probability that the project will be completed in 95 days or less?
(Multiple Choice)
4.7/5
(38)
Describe the differences between a Gantt chart and a PERT/CPM network.