Draw the AOA and AON networks for the following project and calculate the minimum project duration. Draw the AOA and AON networks for the following project and calculate the minimum project duration.

(Essay)
4.8/5
(36)

A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project will be completed before which day (rounded to nearest day)?

(Multiple Choice)
4.9/5
(38)

The expected activity time in PERT analysis is calculated as:

(Multiple Choice)
4.9/5
(30)

Given the project within the table below,calculate the following: a.The critical path b.The minimum project duration c.The amount of slack for each activity Given the project within the table below,calculate the following: a.The critical path b.The minimum project duration c.The amount of slack for each activity

(Essay)
4.9/5
(38)

A network consists of the following list.Times are given in weeks. A network consists of the following list.Times are given in weeks.    a.Draw the network diagram. b.Which activities form the critical path? c.How much slack exists at activities A and F? d.What is the duration of the critical path? a.Draw the network diagram. b.Which activities form the critical path? c.How much slack exists at activities A and F? d.What is the duration of the critical path?

(Essay)
4.8/5
(37)

Which of the following statements regarding PERT analysis is true?

(Multiple Choice)
4.8/5
(37)

Contract requirements state that a project must be completed within 180 working days,or it will incur penalties for late completion.Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400.What is the probability that the project will be completed before the late-payment deadline?

(Multiple Choice)
4.9/5
(37)

An activity on a PERT network has these time estimates: optimistic = 2,most likely = 3,and pessimistic = 8.What is its expected activity time and variance?

(Multiple Choice)
4.9/5
(41)

Activity D on a CPM network has predecessors B and C,and has successor F.D has duration 6.B's earliest finish is 18,while C's is 20.F's late start is 26.Which of the following is definitely true?

(Multiple Choice)
4.7/5
(38)

Which of the following is NOT one of the phases of project management?

(Multiple Choice)
5.0/5
(31)

Describe some of the challenges faced in the construction of the new 11-story building at Arnold Palmer Hospital in Orlando,Florida.

(Essay)
4.7/5
(28)

An activity on a PERT network has these time estimates: optimistic = 2,most likely = 5,and pessimistic = 10.What is its expected activity time?

(Multiple Choice)
4.8/5
(33)

Every network has at least one critical path.

(True/False)
4.7/5
(34)

A project organization works best for an organization when the project resides in only one of its functional areas.

(True/False)
4.8/5
(38)

One phase of a large project is scheduling.

(True/False)
4.8/5
(38)

Describe in words how to calculate a project's standard deviation.What assumption allows that calculation to be accurate?

(Essay)
4.7/5
(36)

Identify the responsibilities of project managers.

(Essay)
4.9/5
(30)

________ is decreasing activity time in a network to reduce time on the critical path so total completion time is reduced.

(Essay)
4.8/5
(37)

A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before which day (rounded to nearest day)?

(Multiple Choice)
4.9/5
(39)

Define slack time.

(Short Answer)
5.0/5
(39)