Exam 3: Project Management
Exam 1: Operations and Productivity127 Questions
Exam 2: Operations Strategy in a Global Environment119 Questions
Exam 3: Project Management120 Questions
Exam 4: Forecasting141 Questions
Exam 5: Design of Goods and Services118 Questions
Exam 6: Managing Quality127 Questions
Exam 7: Process Strategy108 Questions
Exam 8: Location Strategies120 Questions
Exam 9: Layout Strategies145 Questions
Exam 10: Human Resources,job Design,and Work Measurement154 Questions
Exam 11: Supply Chain Management145 Questions
Exam 12: Inventory Management163 Questions
Exam 13: Aggregate Planning and Sop116 Questions
Exam 14: Material Requirements Planning Mrpand Erp116 Questions
Exam 15: Short-Term Scheduling115 Questions
Exam 16: Jit,tps,and Lean Operations115 Questions
Exam 17: Maintenance and Reliability111 Questions
Exam 18: Sustainability in the Supply Chain80 Questions
Exam 19: Statistical Process Control144 Questions
Exam 20: Capacity and Constraint Management96 Questions
Exam 21: Supply Chain Management Analytics55 Questions
Exam 22: Decision-Making Tools96 Questions
Exam 23: Linear Programming88 Questions
Exam 24: Transportation Models89 Questions
Exam 25: Waiting-Line Models119 Questions
Exam 26: Learning Curves110 Questions
Exam 27: Simulation74 Questions
Select questions type
Draw the AOA and AON networks for the following project and calculate the minimum project duration.


(Essay)
4.8/5
(36)
A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project will be completed before which day (rounded to nearest day)?
(Multiple Choice)
4.9/5
(38)
The expected activity time in PERT analysis is calculated as:
(Multiple Choice)
4.9/5
(30)
Given the project within the table below,calculate the following:
a.The critical path
b.The minimum project duration
c.The amount of slack for each activity


(Essay)
4.9/5
(38)
A network consists of the following list.Times are given in weeks.
a.Draw the network diagram.
b.Which activities form the critical path?
c.How much slack exists at activities A and F?
d.What is the duration of the critical path?

(Essay)
4.8/5
(37)
Which of the following statements regarding PERT analysis is true?
(Multiple Choice)
4.8/5
(37)
Contract requirements state that a project must be completed within 180 working days,or it will incur penalties for late completion.Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400.What is the probability that the project will be completed before the late-payment deadline?
(Multiple Choice)
4.9/5
(37)
An activity on a PERT network has these time estimates: optimistic = 2,most likely = 3,and pessimistic = 8.What is its expected activity time and variance?
(Multiple Choice)
4.9/5
(41)
Activity D on a CPM network has predecessors B and C,and has successor F.D has duration 6.B's earliest finish is 18,while C's is 20.F's late start is 26.Which of the following is definitely true?
(Multiple Choice)
4.7/5
(38)
Which of the following is NOT one of the phases of project management?
(Multiple Choice)
5.0/5
(31)
Describe some of the challenges faced in the construction of the new 11-story building at Arnold Palmer Hospital in Orlando,Florida.
(Essay)
4.7/5
(28)
An activity on a PERT network has these time estimates: optimistic = 2,most likely = 5,and pessimistic = 10.What is its expected activity time?
(Multiple Choice)
4.8/5
(33)
A project organization works best for an organization when the project resides in only one of its functional areas.
(True/False)
4.8/5
(38)
Describe in words how to calculate a project's standard deviation.What assumption allows that calculation to be accurate?
(Essay)
4.7/5
(36)
________ is decreasing activity time in a network to reduce time on the critical path so total completion time is reduced.
(Essay)
4.8/5
(37)
A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before which day (rounded to nearest day)?
(Multiple Choice)
4.9/5
(39)
Showing 61 - 80 of 120
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)