Exam 14: Materials and Resource Requirements Planning
Exam 1: Introduction to Managing Operations Across the Supply Chain40 Questions
Exam 2: Operations and Supply Chain Strategy25 Questions
Exam 3: Managing Processes and Capacity29 Questions
Exam 3: A: Process Mapping and Analysis31 Questions
Exam 4: Productprocess Innovation43 Questions
Exam 5: Manufacturing and Service Process Structures53 Questions
Exam 6: Managing Quality44 Questions
Exam 6: A: Quality Improvement Tools51 Questions
Exam 7: Managing Inventories32 Questions
Exam 8: Lean Systems57 Questions
Exam 9: Customer Service Management59 Questions
Exam 10: Sourcing and Supply Management50 Questions
Exam 11: Logistics Management39 Questions
Exam 12: Demand Planning: Forecasting and Demand Management44 Questions
Exam 13: Sales and Operations Planning36 Questions
Exam 14: Materials and Resource Requirements Planning33 Questions
Exam 15: Project Management34 Questions
Exam 15: A: Advanced Methods for Project Scheduling40 Questions
Exam 16: Sustainable Operations Management Preparing for the Future39 Questions
Select questions type
In evaluating time-cost trade-offs,we start by crashing the task on the critical path that:
(Multiple Choice)
4.9/5
(29)
A project manager has discovered that three tasks are on the critical path for a particular project.She has developed the time estimates (in days)shown in the table below.
The customer has offered a $10,000 bonus if the project is completed within 14 days.What is the probability that the bonus will be earned?

(Multiple Choice)
4.8/5
(36)
Annie is planning a large surprise party for her sister Gwendolyn.She has developed the following plan,including estimates of the time (in hours)and cost necessary to perform each of the tasks required.
What is the planned duration of the preparation for the surprise party,assuming the critical path is completed?

(Multiple Choice)
4.9/5
(43)
A project manager has discovered that three tasks are on the critical path for a particular project.She has developed the time estimates (in days)shown in the table below.Complete the table and determine the expected completion time for the project. 

(Multiple Choice)
5.0/5
(39)
Task X has a best-case duration of 4 days,a worst-case duration of 10 days,and a most likely duration of 6 days.Using this information,we can estimate a 50 percent probability that the task will be completed in no more than how many days?
(Multiple Choice)
4.7/5
(31)
Given the tasks,estimated durations,and crash costs shown below,what would be the minimum cost to reduce the project by one day? 

(Multiple Choice)
4.8/5
(42)
Task X has an 82 percent probability that it will be completed in 20 days or less.The standard deviation of its duration is five days.What is its expected duration?
(Multiple Choice)
4.9/5
(43)
Identify the critical path to completion for the project plan.


(Multiple Choice)
4.9/5
(43)
An estimate of the duration of a task that is based on a weighted average of a range of possible task durations is known as:
(Multiple Choice)
4.7/5
(36)
Task X has a most likely duration of 10 days,a best-case duration of 8 days,and a worst-case duration of 15 days.What is the probability that it will be completed in 12 days or less?
(Multiple Choice)
4.9/5
(34)
For a project with many task paths of nearly equal lengths,the best way to estimate the probabilities associated with project completion is:
(Multiple Choice)
4.8/5
(35)
A simple sequential project (each task must be completed before the next one can begin)has the time estimates (in days)shown below:
What is the expected total time for the project?

(Multiple Choice)
4.8/5
(36)
Annie is planning a large surprise party for her sister Gwendolyn.She has developed the following plan,including estimates of the time (in hours)and cost necessary to perform each of the tasks required.
If Annie has already crashed task A to its minimum duration,what is the next task she should crash?

(Multiple Choice)
4.8/5
(43)