Exam 14: Materials and Resource Requirements Planning

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

In evaluating time-cost trade-offs,we start by crashing the task on the critical path that:

(Multiple Choice)
4.9/5
(29)

A project manager has discovered that three tasks are on the critical path for a particular project.She has developed the time estimates (in days)shown in the table below. A project manager has discovered that three tasks are on the critical path for a particular project.She has developed the time estimates (in days)shown in the table below.   The customer has offered a $10,000 bonus if the project is completed within 14 days.What is the probability that the bonus will be earned? The customer has offered a $10,000 bonus if the project is completed within 14 days.What is the probability that the bonus will be earned?

(Multiple Choice)
4.8/5
(36)

Annie is planning a large surprise party for her sister Gwendolyn.She has developed the following plan,including estimates of the time (in hours)and cost necessary to perform each of the tasks required. Annie is planning a large surprise party for her sister Gwendolyn.She has developed the following plan,including estimates of the time (in hours)and cost necessary to perform each of the tasks required.   What is the planned duration of the preparation for the surprise party,assuming the critical path is completed? What is the planned duration of the preparation for the surprise party,assuming the critical path is completed?

(Multiple Choice)
4.9/5
(43)

A project manager has discovered that three tasks are on the critical path for a particular project.She has developed the time estimates (in days)shown in the table below.Complete the table and determine the expected completion time for the project. A project manager has discovered that three tasks are on the critical path for a particular project.She has developed the time estimates (in days)shown in the table below.Complete the table and determine the expected completion time for the project.

(Multiple Choice)
5.0/5
(39)

Task X has a best-case duration of 4 days,a worst-case duration of 10 days,and a most likely duration of 6 days.Using this information,we can estimate a 50 percent probability that the task will be completed in no more than how many days?

(Multiple Choice)
4.7/5
(31)

Given the tasks,estimated durations,and crash costs shown below,what would be the minimum cost to reduce the project by one day? Given the tasks,estimated durations,and crash costs shown below,what would be the minimum cost to reduce the project by one day?

(Multiple Choice)
4.8/5
(42)

Task X has an 82 percent probability that it will be completed in 20 days or less.The standard deviation of its duration is five days.What is its expected duration?

(Multiple Choice)
4.9/5
(43)

    Identify the critical path to completion for the project plan.     Identify the critical path to completion for the project plan. Identify the critical path to completion for the project plan.

(Multiple Choice)
4.9/5
(43)

An estimate of the duration of a task that is based on a weighted average of a range of possible task durations is known as:

(Multiple Choice)
4.7/5
(36)

Task X has a most likely duration of 10 days,a best-case duration of 8 days,and a worst-case duration of 15 days.What is the probability that it will be completed in 12 days or less?

(Multiple Choice)
4.9/5
(34)

For a project with many task paths of nearly equal lengths,the best way to estimate the probabilities associated with project completion is:

(Multiple Choice)
4.8/5
(35)

A simple sequential project (each task must be completed before the next one can begin)has the time estimates (in days)shown below: A simple sequential project (each task must be completed before the next one can begin)has the time estimates (in days)shown below:   What is the expected total time for the project? What is the expected total time for the project?

(Multiple Choice)
4.8/5
(36)

Annie is planning a large surprise party for her sister Gwendolyn.She has developed the following plan,including estimates of the time (in hours)and cost necessary to perform each of the tasks required. Annie is planning a large surprise party for her sister Gwendolyn.She has developed the following plan,including estimates of the time (in hours)and cost necessary to perform each of the tasks required.   If Annie has already crashed task A to its minimum duration,what is the next task she should crash? If Annie has already crashed task A to its minimum duration,what is the next task she should crash?

(Multiple Choice)
4.8/5
(43)
Showing 21 - 33 of 33
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)